West 41st Street Bridge in the City of Cleveland

  • Notice to Proceed: 10/1/2018
  • Start Date: 8/29/2018
  • Completion Date: 11/1/2018
  • Project Amount: $686,326.80
  • This Page Last Updated On: 2/12/2019

Contractor:
Becdir Construction Company
(216) 247-7705

County Project Contacts: 
Jaoudat Charif (216) 701-1262
Bill Nugent (216) 556-4617

Notice to Proceed: October 2018
Contract Award Amount:  $686,326.80

Start Date:  August 29, 2018  

Scheduled Completion Date:
November 2018 

Approved Contract Increases:  $0

Approved Contract Decreases:  $ 0

Anticipated Completion Date: January 2019

Estimated Cost to Completion:   $686,326.80


PROGRESS:

February 12, 2019
  • Completed installing new bearing pad anchor bolts at the pier caps.
  • Completed installing new epoxy coated reinforcing for pier cap modifications on pier #5, #6 and #7. 
  • Form pier caps for new concrete at pier’s #5, #6 and #7
  • Install new strip seal at the forward and rear abutment expansion joint. 
  • Remove concrete forms and finish concrete surface on the pier caps. 
  • Install anchor bolts for bearing pads. 
One Month Look Ahead:
  • Perform concrete removal and patching on piers.
  • Grind and rub out concrete imperfections at pier cap modifications.
  • Open structure to traffic.
  • Remove detour route.
  • Perform clean-up of staging and storage yard.
Notes:
  • Permanent striping placement will be completed in spring 2019.
  • Final landscaping (seed/mulch) will be completed spring 2019.
  • Project is substantially completed. Remainder of work to be completed in spring with minimal impact on traffic. 
Maintenance of Traffic:
  • Roadway to stay open at all times.

January 4, 2019
  • Completed removing unsound concrete from the rear and forward abutments and approach slabs. Concrete was then placed in the repair area. 
  • Jacking operation was performed, and new bearings were installed on pier caps at pier 1, 2, 3, 5, 6, and 7 forward and rear abutments.  
  • Started the installation of bearing pad anchor bolts. 
  • Installing new epoxy coated reinforcing steel to pier cap modifications at pier 5, 6 and 7. 
One Month Look Ahead:
  • Finish installing new bearing pad anchor bolts at the caps. 
  • Finish installing new epoxy coated reinforcing for pier cap modifications on pier 5,6, and 7.
  • Form pier caps for new concrete at pier 5, 6, and 7. 
  • Install new strip seal at the forward and rear abutment expansion joint. 
  • Remove concrete forms and finish concrete surface on the pier caps.