You are here: Home > Projects & Programs > Construction Updates 

Stone Road Bridge No. 00.98 City of Independence

  • Notice to Proceed: 8/1/2018
  • Start Date: 9/1/2018
  • Completion Date: 7/1/2019
  • Project Amount: $1,239,932.45
  • This Page Last Updated On: 5/8/2019
Contractor:
Schirmer Construction, LLC

County Project Contacts:
 
Ryan Maver (216) 556-3932
Craig Berger (216) 280-5696

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
July 2019

Estimated Cost to Completion: $1,239,932.45

PROGRESS


May 8, 2019

PROGRESS:

· General contractor has completed Stone Road Bridge deck and has transitioned to work on roadway surface and subgrade.

· Once asphalt road surface is complete the contractor will then move traffic to new pavement and begin work on storm and bike path along north side of Stone Road.

April 11, 2019

  • Contractor has completed Phase I of bridge deck and have successfully transitioned traffic to new bridge.
  • Phase 2 bridge deck construction has been completed. Drainage and roadway work will begin.