Snow Road Bridge #220 Rehabilitation

  • Notice to Proceed: 6/4/2012
  • Start Date: 6/25/2012
  • Completion Date: 11/2/2012
  • Project Amount: $229,995.50
  • This Page Last Updated On: 9/5/2012
  • Contractor:
    Geotech Inc
    (440) 439-1544
  • Conty Project Contacts: 
    Terry Cain (216) 857-4056 
    Joe Charif (216) 701-1262
  • Approved Contract Increases: None
  • Approved Contract Decreases: None

Progress

September 5, 2012
  • Project has been completed.


August 20, 2012

  • Contractor is currently working on the east side corrugated culvert pipe.
  • Invert of pipe cleaned, new corrugated plates being welded over deteriorated areas.
  • Following welding of plates, invert of pipe will be paved with concrete.
  • All work is being completed underground-Snow Rd. traffic is not affected.


July 3, 2012

  • The west side corrugated culvert pipe has been rehabilitated. Contractor is currently working on the east side pipe. All work is underground and Snow Road traffic is not affected.