Snow Road Bridge #220 Rehabilitation
- Notice to Proceed: 6/4/2012
- Start Date: 6/25/2012
- Completion Date: 11/2/2012
- Project Amount: $229,995.50
- This Page Last Updated On: 9/5/2012
- Contractor:
Geotech Inc
(440) 439-1544
- Conty Project Contacts:
Terry Cain (216) 857-4056
Joe Charif (216) 701-1262
- Approved Contract Increases: None
- Approved Contract Decreases: None
Progress
September 5, 2012
- Project has been completed.
August 20, 2012
- Contractor is currently working on the east side corrugated culvert pipe.
- Invert of pipe cleaned, new corrugated plates being welded over deteriorated areas.
- Following welding of plates, invert of pipe will be paved with concrete.
- All work is being completed underground-Snow Rd. traffic is not affected.
July 3, 2012
- The west side corrugated culvert pipe has been rehabilitated. Contractor is currently working on the east side pipe. All work is underground and Snow Road traffic is not affected.