Cedar Road (I-271 to Green Road) Cities of Lyndhurst, Beachwood, South Euclid & University Heights

  • Notice to Proceed: 3/1/2019
  • Start Date: 3/1/2019
  • Completion Date: 6/1/2020
  • Project Amount: $4,499,104.25
  • This Page Last Updated On: 4/11/2019
Contractor:
Perk Construction
(216) 391-1444

County Project Contacts: 
Ramzi Halasah (216) 795-5477
Ryan Maver (440) 759-2472

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
June 2020

Estimated Cost to Completion: $4,499,104.25

PROGRESS

May 8, 2019

Phase 1B: (Green Road to Richmond Road):

· Anew zone was implemented on 5/7/18 with two-way traffic now being maintained on the northern one half of Cedar Road as repairs are being performed on the south one half.

· Turning lanes have been provided at Green Road, Legacy Village (E) main entrance, and at Richmond Road.

Work expected in the coming months:

· Milling of existing asphalt bae material.

· Existing brick and concrete base and curb to be inspected and marked for full depth repairs/replacement.

· Excavation and installation for new 12” concrete base “bus pads” at designated locations along the south side of Cedar Road.

· Placement if intermediate course asphalt followed by adjustment of roadway castings.

· Installation of ADA compliant curb ramps and sidewalks followed by seeding and mulching.

· Note: Designated construction zones will reduce traffic to 50% compacity; with two-way traffic to be always maintained.

· SIGNIFICANT TRAFFIC CONGESTION IS ANTICIPATED FOR THE DURTATION OF THE PROJECT.

April 11, 2019

    Phase 1A: (Green Road to Richmond Road): 
    • Two-way traffic is being maintained on the southern one half of Cedar Road as repairs are being performed on the north one half.
    • Turning lanes have been provided at Green Road, Legacy Village (E) main entrance, and at Richmond Road. 
    Work expected in the coming months: 
    • Milling of existing asphalt bae material
    • Removal and replacement of existing 2.5’ gutter, curb and driveway aprons along the south side of Cedar.
    • North one half of roadway; Existing brick and concrete base is being inspected and marked for full depth repairs/replacement.
    • Placement of intermediate course asphalt followed by adjustment of roadway castings.
    • Note: Designated construction zones will reduce traffic to 50% compacity; with two-way traffic to be always maintained.
    • SIGNIFICANT TRAFFIC CONGESTION IS ANTICIPATED FOR THE DURTATION OF THE PROJECT.