Austin Powder Drive Bridge #137 Replacement

  • Notice to Proceed: 6/7/2012
  • Start Date: 7/16/2012
  • Completion Date: 12/1/2012
  • Project Amount: $908,993.93
  • This Page Last Updated On: 11/2/2012
  • Contractor: 
    Suburban Maintenance & Construction, Inc. (440) 237-7765 
  • County Project Contacts:
    Darwin Merdes (216) 348-4073
    Pat Lynch (216) 338-9612 
  • Approved Contract Increases: None
  • Approved Contract Decreases: None
  • Estimated Cost to Completion:  $908,993.93
  • Anticipated Completion Date: December 1, 2012

Progress


November 1, 2012

  • Placement of rear abutment wall, rear wing wall.

October 1, 2012
  • Placement of 12” piles for rear footers.
  • Formworks for proposed rear footers.

August 1, 2012
  • Placement of sheet piling.
  • Shoring for Wheeling/Lake Erie Railroad.
  • Removal of existing guardrail.
  • Demolition of existing structure.

September 5, 2012
  • Placement of sheet piling.
  • Demolition of existing structure.