Austin Powder Drive Bridge #137 Replacement
- Notice to Proceed: 6/7/2012
- Start Date: 7/16/2012
- Completion Date: 12/1/2012
- Project Amount: $908,993.93
- This Page Last Updated On: 11/2/2012
- Contractor:
Suburban Maintenance & Construction, Inc. (440) 237-7765
- County Project Contacts:
Darwin Merdes (216) 348-4073
Pat Lynch (216) 338-9612
- Approved Contract Increases: None
- Approved Contract Decreases: None
- Estimated Cost to Completion: $908,993.93
- Anticipated Completion Date: December 1, 2012
Progress
November 1, 2012
- Placement of rear abutment wall, rear wing wall.
October 1, 2012
- Placement of 12” piles for rear footers.
- Formworks for proposed rear footers.
August 1, 2012
- Placement of sheet piling.
- Shoring for Wheeling/Lake Erie Railroad.
- Removal of existing guardrail.
- Demolition of existing structure.
September 5, 2012
- Placement of sheet piling.
- Demolition of existing structure.