You are here: Home > Projects & Programs > Construction Updates 

West 130th Street From Brook Park Road to Lorain Road Cities of Brook Park and Cleveland

  • Notice to Proceed: 6/1/2016
  • Start Date: 6/1/2016
  • Completion Date: 12/31/2017
  • Project Amount: $7,946,652.90
  • This Page Last Updated On: 10/10/2017
DATE: August 8, 2016

Contractor: 
Perk company 
216-391-1444

County Project Contacts:
Ramzi Halasah
216-536-5345

Notice to Proceed:
June 2016

Contract Award Amount:
$7,946,652.90

Start Date:
June 2016

Approved Contract Increases:

Scheduled Completion Date: 
December 2017 

Approved Contract Decreases: 
$0

Anticipated Completion Date:
December 2017

Estimated Cost to Completion:
$7,946,652.90

Progress:

October 10, 2017
  • Bellaire to Enterprise Avenue has been re-opened to traffic with one center lane for left turns and one lane each for north and southbound traffic.
  • Work on Culvert 11.15 W. 130th Street has begun.
  • The west inlet wall will be cast in place, weather permitting, in the next week.
  • Traffic continues to be maintained both south and northbound from Enterprise Avenue to Brookpark Road, one lane in each direction.
  • Traffic control is being assisted with a traffic control police officer at the entrance/exit ramps of I-480 and W. 130th Street.
September 1, 2017

  • Traffic is being maintained southbound only from Bellaire Road to Enterprise Avenue, until final surface course asphalt is completed, (scheduled for the end of the second week in September).
  • Traffic is maintained in both southbound and northbound directions between Enterprise Avenue and Brookpark Road, but is restricted to one lane in each direction. Traffic control police officers are being used to aid traffic on this area by being stationed at the following intersections;
    • W. 130th Street and Enterprise Avenue
    • W. 130th Street and I-480 exit ramp
    • W. 130th Street and Brookpark Roa
  • Work is being continued at culver 10.60 W. 130th Street. East inlet wall being cast in place and the adjacent road Longmead Avenue will be repaired in the following week.
  • The roadway between Bellaire Road and Enterprise Avenue, is scheduled to be open to two-way traffic by the end of the second week of September weather permitting


June 15, 2017

  • Work is being performed on Section 3 (Bellaire Road to Enterprise Avenue).
  • All curb sidewalks and driveway aprons are completed on the west side and currently working on the east side.
  • Traffic is maintained southbound only.
  • Enterprise Avenue to Brookpark Road is being maintained by two-way traffic.

December 16, 2017
  • Beginning on Friday, December 16th the lane closure at Enterprise and W. 130th Street to Brook Park Road will be open to traffic.
  • Section II will be open to north and south bound traffic on Friday, December 23rd.
  • Beginning on Tuesday, December 20th, Brook Park Road west bound will be restricted to one lane from 8:00 pm to 6:00 am, for the installation of the 12” tee-cut as requested by the Cleveland Water Department. This area will be zoned off and Brook Park Police Officers will be directing traffic.

October 7, 2016
  • The section between I-71 to Lorain Avenue is open to traffic in both directions north and south. This section is substantially complete.
  • Section II from Bellaire to I-71 will be under construction and traffic will be one-way northbound only.
  • Continue to work on sidewalks, aprons and pavement, as well as working on two culvert replacements. This work will continue through the winter months. 

Maintenance of Traffic:

 

  • Traffic will be able travel north and southbound and maintained by temporary signals as culverts.

August 9, 2016

  • Phase B will be implemented on Tuesday, August 9, 2016.
  • Traffic will be shifted to the west lane.  

Maintenance of Traffic:

  • Traffic will continue to be one lane (north) from 1-71 to Lorain Road.