West 130th Street From Brook Park Road to Lorain Road Cities of Brook Park and Cleveland

  • Notice to Proceed: 6/1/2016
  • Start Date: 6/1/2016
  • Completion Date: 12/31/2017
  • Project Amount: $7,946,652.90
  • This Page Last Updated On: 6/15/2017
DATE: August 8, 2016

Contractor: 
Perk company 
216-391-1444

County Project Contacts:
Ramzi Halasah
216-536-5345

Notice to Proceed:
June 2016

Contract Award Amount:
$7,946,652.90

Start Date:
June 2016

Approved Contract Increases:

Scheduled Completion Date: 
December 2017 

Approved Contract Decreases: 
$0

Anticipated Completion Date:
December 2017

Estimated Cost to Completion:
$7,946,652.90

Progress:

June 15, 2017
  • Work is being performed on Section 3 (Bellaire Road to Enterprise Avenue).
  • All curb sidewalks and driveway aprons are completed on the west side and currently working on the east side.
  • Traffic is maintained southbound only.
  • Enterprise Avenue to Brookpark Road is being maintained by two-way traffic.

December 16, 2017
  • Beginning on Friday, December 16th the lane closure at Enterprise and W. 130th Street to Brook Park Road will be open to traffic.
  • Section II will be open to north and south bound traffic on Friday, December 23rd.
  • Beginning on Tuesday, December 20th, Brook Park Road west bound will be restricted to one lane from 8:00 pm to 6:00 am, for the installation of the 12” tee-cut as requested by the Cleveland Water Department. This area will be zoned off and Brook Park Police Officers will be directing traffic.

October 7, 2016
  • The section between I-71 to Lorain Avenue is open to traffic in both directions north and south. This section is substantially complete.
  • Section II from Bellaire to I-71 will be under construction and traffic will be one-way northbound only.
  • Continue to work on sidewalks, aprons and pavement, as well as working on two culvert replacements. This work will continue through the winter months. 

Maintenance of Traffic:

 

  • Traffic will be able travel north and southbound and maintained by temporary signals as culverts.

August 9, 2016

  • Phase B will be implemented on Tuesday, August 9, 2016.
  • Traffic will be shifted to the west lane.  

Maintenance of Traffic:

  • Traffic will continue to be one lane (north) from 1-71 to Lorain Road.