Warrensville Ctr Rd, Maple Hts, Bedord

  • Notice to Proceed: 4/1/2019
  • Start Date: 4/1/2019
  • Completion Date: 11/29/2019
  • Project Amount: $1,239,932.45
  • This Page Last Updated On: 5/7/2019
Contractor: CATTS Construction

County Project Contacts:
 
Ryan Maver (216) 556-3932
Mike Cotter (216) 280-8757

Contract Award Amount: $3,068,000.05

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
July 2019

Estimated Cost to Completion:  $3,068,000.05


May 8, 2019

PROGRESS:

Work Expected in the upcoming weeks will include:

· Intermediate course paving.

· Casting adjustments

· Flipping traffic west side of road.

· Beginning full depth repairs on east side.