- Notice to Proceed: 7/1/2019
- Start Date: 7/1/2019
- Completion Date: 11/1/2020
- Project Amount: $4,560,424.50
- This Page Last Updated On: 12/7/2020
Contractor:
Perk Company Terry Cain 216-633-056
440-891-1444 Joe Charif 440-701-1262
Notice to Proceed: July 2019 Contract Award Amount: $4,560,424.50
Start Date: July 2019 Approved Contract Increases: $0
Scheduled Completion Date: November 2020 Approved Contract Decreases: $0
Anticipated Completion Date: November 2020 Estimated Cost to Completion: $4,560,424.50
PROGRESS:
December:
- Milling of existing asphalt, base repair, casting adjustments and placement of new asphalt has been completed from Bagley Road to Snow Road on the left and right sides.
- A punch list has been compiled and still needs to be completed.
November 6, 2010
- Milling of existing asphalt, base repair, casting adjustments and placement of new asphalt has been completed from Bagley Road to Snow Road on the left and right sides.
- A final walk through and completion of a punch list is forthcoming.
September 10, 2010
- Milling of existing asphalt, base repair, casting adjustments and placement of new asphalt has been completed from Bagley Road to Snow Road on the left and right sides.
- Corrective work to smooth uneven asphalt, seal joints and fix ponding water areas will be performed through this month.
- Placement of permanent striping will be performed.
- A final walk through and completion of a punch list is forthcoming.
August 10, 2020
- Milling of existing asphalt, base repair, casting adjustments and placement of new asphalt has been completed for Bagley Road to Snow Road on the left and right sides.
- Corrective work to smooth uneven asphalt, seal joints and fix ponding water areas will be performed through this month.
- Placement of permanent striping still needs to be completed.
- A final walk through and completion of a punch list is forthcoming.
July 10, 2020
- Milling of existing asphalt, base repair, casting adjustments and placement of new asphalt has been completed from Bagley Road to Snow Road on the left and right sides.
- Placement of permanent striping still needs to be completed.
- A final walk through and compilation a punch list still needs to be completed.
June 3, 2020
- Milling of existing asphalt, base repair, casting adjustments and placement of new asphalt has been completed from Bagley Road to Snow Road on the left and right sides.
- Placement of permanent striping still needs to be completed.
- A final walk through and punch list needs to completed.
May 4, 2020
- New surface course asphalt has been completed from the bridge just north of Bagley Road to just south of Holland/Huffman Roads, on both the left and right sides of W. 130th Street.
- Crosswalk lines, stop lines, lane arrows and channelizing lines have been placed.
April 7, 2020
- New surface course asphalt has been completed from the bridge just north of Bagley Road to just south of Holland/Huffman Roads, on both the left and right sides of W. 130th Street.
- Crosswalk lines, stop lines, lane arrows and channelizing lines have been placed.
March 5, 2020
- New surface course asphalt has been completed from the bridge just north of Bagley Road to just south of Holland/Huffman Roads, on both the left and right sides of W. 130th Street.
- Crosswalk lines, stop lines, lane arrows and channelizing lines have been placed.
- Project is shut down until spring.
- Contractor is planning on returning in mid-March.
January 13, 2020
- New surface course asphalt has been completed from the bridge just north of Bagley Road to just south of Holland/Huffman Roads, on both the left and right sides of W. 130th Street.
- Crosswalk lines, stop lines, lane arrows and channelizing lines have been placed.
- Project is shut down until spring.
November 5, 2019
- New surface course asphalt will be placed next week from the bridge north of Bagley Road, just north of Big Creek Parkway. This will complete this part of the project.
- The existing asphalt has now been removed on the east side of W. 130th Street, just north of Big Creek Parkway to just south of Huffman Road.
- Base repairs and castings adjustments are being completed, new surface asphalt will be placed next week.
- The west side will be milled and 3” of existing asphalt will be removed next week.
- This section is scheduled to be completed by the end of November.
August 6, 2019
- Two-way Traffic is being maintained for Phase A construction on the west side of W. 130th Street from Bagley Road to the Metroparks Parkway.
- Phase A asphalt wearing course removal has been completed.
- Full depth concrete repairs have begun starting at Bagley Roan and moving northward