W.130th Street Resurfacing Project

  • Notice to Proceed: 8/6/2019
  • Start Date: 8/6/2019
  • Completion Date: 11/1/2020
  • Project Amount: $4,560,424.50
  • This Page Last Updated On: 3/5/2020
Contractor:                                                              County Project Contacts:
Perk Company                                                          Terry Cain   216-633-056
440 891-1444                                                            Joe Charif   440-701-1262

Notice to Proceed: July 2019                                      Contract Award Amount: $4,560,424.50

Start Date:
July 2019                                                    Approved Contract Increases: $0

Scheduled Completion Date:  November 2020          Approved Contract Decreases: $0 

Anticipated Completion Date:  November 2020         Estimated Cost to Completion:  $4,560,424.50

PROGRESS:

March 5, 2020

  • New surface course asphalt has been completed from the bridge just north of Bagley Road to just south of Holland/Huffman Roads, on both the left and right sides of W. 130th Street.
  • Crosswalk lines, stop lines, lane arrows and channelizing lines have been placed.
  • Project is shut down until spring.
  • Contractor is planning on returning in mid-March.

January 13, 2020

  • New surface course asphalt has been completed from the bridge just north of Bagley Road to just south of Holland/Huffman Roads, on both the left and right sides of W. 130th Street.
  • Crosswalk lines, stop lines, lane arrows and channelizing lines have been placed.
  • Project is shut down until spring.

November 5, 2019

  • New surface course asphalt will be placed next week from the bridge north of Bagley Road, just north of Big Creek Parkway. This will complete this part of the project.
  • The existing asphalt has now been removed on the east side of W. 130th Street, just north of Big Creek Parkway to just south of Huffman Road.
  • Base repairs and castings adjustments are being completed, new surface asphalt will be placed next week.
  • The west side will be milled and 3” of existing asphalt will be removed next week.
  • This section is scheduled to be completed by the end of November.

August 6, 2019

  • Two-way Traffic is being maintained for Phase A construction on the west side of W. 130th Street from Bagley Road to the Metroparks Parkway.
  • Phase A asphalt wearing course removal has been completed.
  • Full depth concrete repairs have begun starting at Bagley Roan and moving northward