Turney Rd /Hathaway Road - Garfield Heights

  • Notice to Proceed: 3/3/2017
  • Start Date: 4/3/2017
  • Completion Date: 9/3/2017
  • Project Amount: $6,913,335.59
  • This Page Last Updated On: 9/7/2017


Date:
May 2, 2017

Contractor: Perk Construction Company

County Project Contacts:

Darwin Merdes 216 348-4073
Patrick Lynch 216-338-9612

Notice to Proceed: March 2017

Contract Award Amount:  $6,913,335.59

Start Date: April  2017

Approved Contract Increases:  $0

Scheduled Completion Date: September 2018
Approved Contract Decreases:  $0

Anticipated Completion Date: September 2018
Estimated Cost to Completion:   $6,913,335.59

Description:

Rehabilitation of 3.40 miles of Turney Road from Warner Road to Hathaway Road excluding bridge over I-480. Major work items include: Partial and full depth pavement repair, curb repair, curb ramps, traffic loop detectors, signs, and manhole, catch basin, and water valve adjustments to grade.

Progress:

September 7, 2017

  • Current zone: Section 3, Phase 2, from I-480 to Plymouth Avenue. Traffic maintained in one lane northbound and southbound in the southbound lanes.
  • Current work: Wearing surface removed, full depth and partial depth pavement repairs and curb repairs in progress.

August 3, 2017

  • Wearing surface removed, full depth pavement repairs complete, partial depth pavement in progress, intermediate course asphalt scheduled for August 3, 2017.
  • Current Zone:
  • Section 3, Phase 1: from I-480 to Plymouth Avenue.
  • Traffic maintained in one lane north and southbound in the southbound lanes.
July 7, 2017

Description:
Pavement planning of .44 miles of Hathaway Road, repair of deteriorated base course, removal and replacement of abutting drive aprons, construction of a uniform 3” asphalt concrete overlay.

Progress:

  • Completed paved shoulder construction, completion of base pavement repairs, completion of intermediate course asphalt concrete placement.
  • Current work included drive apron replacement, catch basin and casting adjustments/reconstructions.

Current Zone:

  • Roadway is open to two-way traffic
  • Existing asphalt pavement milled to concrete base, Section 4, Phase 2, begin full depth/partial depth pavement repairs.
  • Curb repaired, curb aprons completed, intermediate course asphalt Section 4,
    Phase 1.

Current Zone:

  • Section 4, Phase 2 from Hathaway Road to I-480;
  • Traffic maintained in one lane north and southbound in the southbound lanes.

May 3, 2017

  • Existing asphalt pavement milled to concrete base. Replacement of curb, full depth pavement repairs, placement of intermediate course asphalt.

Current Zone:

  • Section 4, Phase I from Hathaway Road to I-480;