Towpath Trail Stage 1 from Harvard Avenue to Steelyard Commons

  • Notice to Proceed: 6/1/2018
  • Start Date: 6/1/2018
  • Completion Date: 12/1/2019
  • Project Amount: $3,561,561.00
  • This Page Last Updated On: 2/14/2019
Contractor:
The Great Lakes Construction Co.
(419) 663-2457

County Project Contacts: 
Darwin Merdes (216) 348-4073
Calvin Overmyer (419) 706-0972

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
December 2019

Estimated Cost to Completion: $3,561,561.00

PROGRESS

February 14, 2019
  • Project is in progress, however shut-down for the winter. 
  • There have been delays; Utility, both gas line and overhead electrical line conflicts and concerns as well as grade issues for the path alignment. These issues are currently being reviewd.  
  • The Harvard Road pedestrian bridge is in place and work to resume on in spring. 
  • Jennings Road work is in progress-roadway is out and temporary fill is in place in addition to maintenance of traffic signals, barrels, and barricades have been placed. 

January 22, 2019
  • Project is in progress, however shut-down for the winter. 
  • Work may resume at any time due to weather conditions and availability of work items that can be performed. 
  • Work that has been performed at this time included removal of pavement through Jennings Avenue. 
  • Installation of the pedestrian bridge superstructure adjacent to the existing Harvard Road Bridge. 
  • Installation work of catch basins, man-holes, and connecting conduits has been performed on Jennings Ave., and to be performed on Harvard Road. 
  • Coordination efforts with the railroad for track and gate work is ongoing,  
  • Not formally scheduled, possible roadway closures.