Towpath Trail stage 1 Harvard Avenue to Steelyard Commons

  • Notice to Proceed: 6/1/2018
  • Start Date: 6/1/2018
  • Completion Date: 12/1/2019
  • Project Amount: $3,561,561.00
  • This Page Last Updated On: 4/7/2020

Contractor:
The Great Lakes Construction Co.: 419-663-2457

County Project Contacts:
Darwin Merdes: 216-348-4073
Calvin Overmyer: 216-772-2191

Approved Contract Increases:
$0

Approved Contract Decreases:
$0


PROGRESS:

April 7, 2020

  • The emergency repair work at the pump station has been completed.
  • The outstanding railroad work is in progress and being performed by the respective railroads. This work is scheduled to be completed approximately mid-April.
  • Pavemenrt and road striping work to be completed.