Stone Road Bridge No. 0098 in City of Independence

  • Notice to Proceed: 8/1/2018
  • Start Date: 9/1/2018
  • Completion Date: 7/1/2019
  • Project Amount: $1,239,932.45
  • This Page Last Updated On: 3/11/2019

Contractor:
Schirmer Construction, LLC

County Project Contacts: 
Ryan Maver (216) 556-3932
Craig Berger (216) 280-5696

Notice to Proceed: August 2018
Contract Award Amount:  $1,239,932.45

Start Date:  September 2018  

Scheduled Completion Date:
July 2019 

Approved Contract Increases:  $0

Approved Contract Decreases:  $ 0

Anticipated Completion Date: July 2019

Estimated Cost to Completion:   $1,239,932.45


PROGRESS:

March 11, 2019
  • General contractor has completed phase I of bridge deck and have successfully transitioned traffic to new bridge.
  • Contractor will be completing Phase II of construction building the second half of Stone Road Bridge over Hemlock Creek.
  • Bridge abutments for Phase II are completed as well as box beams.
  • Concrete will be placed for the bridge deck and approach slabs.
  • Next step in completion is working on roadway surface replacement.  
February 6, 2019
  • Schirmer Construction has completed Phase l of bridge deck and have successfully transitioned traffic to new bridge.
  • Contractor has demolished Phase II of Old Stone Road Bridge to begin construction.
  • There was a slight delay due to weather and equipment malfunction.
  • Driving piles and forming Phase II abutments will begin.

January 4, 2019

  • Schirmer Construction, is on schedule to complete project with Phase I of bridge construction.
  • Traffic has shifted from existing Stone Road Bridge to newly constructed bridge, with temporary pavement to maintain traffic through area with minimal impact to residents.
  • Construction has begun on Phase 2 with demolition of existing Stone Road Bridge, and will continue throughout the winter to maintain project timeline and completion.