Sprague Road Widening

  • Notice to Proceed: 9/1/2019
  • Start Date: 9/1/2019
  • Completion Date: 8/1/2021
  • Project Amount: $7,347,866.50
  • This Page Last Updated On: 4/7/2020

Contractor:
Fabrizi Recycling

County Project Contacts:
Ryan Maver: 216-556-3932
Craig Berger: 216-280-5696

Approved Contract Increases:
$292,847.72

Approved Contract Decreases:
$0


PROGRESS:

April 7, 2020

  • General contractor has completed all waterline installation and converted all homes to new watermain.
  • Storm sewer installation is completed.
  • Contractor will remove existing pavement and prepare subbase for new concrete pavement.
  • All Sprague Road residents’ mailboxes between West 130th Street and Webster Road have been located to Webster Road with a turnout for easy mail collection.