Sprague Road Widening

  • Notice to Proceed: 9/1/2019
  • Start Date: 9/1/2019
  • Completion Date: 8/1/2021
  • Project Amount: $7,347,866.50
  • This Page Last Updated On: 11/16/2020


Contractor:
Fabrizi Recycling

County Project Contacts:
Ryan Maver: 216-556-3932
Craig Berger: 216-280-5696

Approved Contract Increases:
$292,847.72

Approved Contract Decreases:
$0
Estimated Cost to Completion:
$7,640,714.22

PROGRESS:

November 16, 2020

  • General contractor is continuing to work on the widening of Sprague Road and West 10th Street intersection.
  • Sub-contractor Trafftech will be installing signals after concrete is complete.
  • Grass seed has been placed for most of the Middleburg Heights side of Sprague Road apart from a few areas not completed due to contractor having equipment in the area.
  • Expect to have all landscaping completed with in the month of November (excluding the corners of intersection).
  • Weather permitting Sprague Road will be open in both directions of traffic once temporary striping is completed prior to winter.
  • installation begins the week of November 16th.

October 15, 2020

  • General contractor has completed the Strongsville side of the roadway, sidewalk, and final grass between W. 130th Street and Webster Road.
  • The roadway is complete along with drive aprons for residents on Middleburg Heights side of the project.
  • Contractor is working to complete all sidewalks on the Middleburg Heights side and will move on to the landscaping once completed.
  • Contractor will be ordering new mailboxes for residents.
  • Contractor will remove existing pavement and prepare subbase for new concrete pavement.


August 13, 2020

  • General contractor has completed the Strongsville side of roadway, sidewalk, and final grass between W. 130th Street and Webster Road.
  • Contractor continues to work through the summer with concrete placement for roadway along Middleburgh Heights side of Sprague Road.

    Upcoming Work:
  • Complete the intersection of Sprague Road and W. 130th Street and roadway work between north and south construction limits along W. 130th Street.
  • Contractor is working to expedite completion of project to limit the disruption to local traffic.

April 7, 2020

  • General contractor has completed all waterline installation and converted all homes to new watermain.
  • Storm sewer installation is completed.
  • Contractor will remove existing pavement and prepare subbase for new concrete pavement.