Royalton Road 130th St. to York Rd. - North Royalton

  • Notice to Proceed: 11/1/2018
  • Start Date: 11/1/2018
  • Completion Date: 7/1/2021
  • Project Amount: $14,658.155.85
  • This Page Last Updated On: 5/4/2020

Date: May 4, 2020

Contractor: DiGioia-Suburban Excavating, LLC   440-237-1978  

County Project Contacts: 

 Ryan Maver  216-556-393              Todd Zima    440-884-3356

Notice to Proceed:    November 2018

Contract Award Amount: $14,658.155.85

Start Date:  November 2018                               Approved Contract Increases:  $0

Scheduled Completion Date:    July 2021         Approved Contract Decreases:   $0                                   

Anticipated Completion Date:  July 2021    

Estimated Cost to Completion: $14,658,155.85

PROGRESS:

  • Work is ongoing in Section 2B from North Royalton School Bus Garage to
    York Road SOUTH SIDE.
  • Intermediate Asphalt Complete
  • Casting adjustments in process
  • Plan to start driveways and sidewalk

    Expected Work:

  • Complete the driveways and sidewalk,
  • Working towards placing traffic on the south side and working on the north section from the bus garage to York Road.