Many County buildings are currently closed to the public. Please visit our Online services page for resources and building information.

You are here: Home > Projects & Programs > Construction Updates 

Royalton Road 130th St. to York Rd. - North Royalton

  • Notice to Proceed: 11/1/2018
  • Start Date: 11/1/2018
  • Completion Date: 7/1/2021
  • Project Amount: $14,658.155.85
  • This Page Last Updated On: 8/11/2020

Date: May 4, 2020

Contractor: DiGioia-Suburban Excavating, LLC   440-237-1978  

County Project Contacts: 

 Ryan Maver  216-556-393              Todd Zima    440-884-3356

Notice to Proceed:    November 2018

Contract Award Amount: $14,658.155.85

Start Date:  November 2018                               Approved Contract Increases:  $0

Scheduled Completion Date:    July 2021         Approved Contract Decreases:   $0                                   

Anticipated Completion Date:  July 2021    

Estimated Cost to Completion: $14,658,155.85

PROGRESS:

August 11, 2020

  • Base and intermediate course for Section II from York Road to North Royalton Bus Garage has been completed.
  • Permanent striping on Section I from West 130th Street to North Royalton Bus Garage has been completed.
  • The next 30 days; raise castings in Section II on north side, begin to excavate, form and pour sidewalks and driveway aprons.

July 10, 2020

  • Traffic in section 2 on the south side of the road (Section 2 is from the North Royalton Bus Garage to York Road).
  • Cement stabilization will occur the week of July 6th. Drive access will be impacted as well as short duration's that access will be limited.
  • 304 aggregate base and under-drain from July 13th to approximately July 21st.
  • New concrete curb will be placed tentatively July 22nd and 23rd.
  • Asphalt base and intermediate course is tentatively scheduled for the week of July 27th. Drive access will be impacted as well as short duration's that access will be limited.

May, 2020

  • Work is ongoing in Section 2B from North Royalton School Bus Garage to
    York Road SOUTH SIDE.
  • Intermediate Asphalt Complete
  • Casting adjustments in process
  • Plan to start driveways and sidewalk

    Expected Work:

  • Complete the driveways and sidewalk,
  • Working towards placing traffic on the south side and working on the north section from the bus garage to York Road.