You are here: Home > Projects & Programs > Construction Updates 

Royalton Road From 130th Street to York Road in the City of North Royalton

  • Notice to Proceed: 11/1/2018
  • Start Date: 11/1/2018
  • Completion Date: 7/1/2021
  • Project Amount: $14,658,155.85
  • This Page Last Updated On: 11/6/2019

Contractor:
DiGioia-Suburban Excavating, LLC
(440) 237-1978

County Project Contacts: 
Ryan Maver (216) 556-3932
Todd Zima (440) 628-9229

Notice to Proceed: November 2018

Contract Award Amount:
  $14,658,155.85

Start Date:  November 2018  

Scheduled Completion Date:
July 2021 

Approved Contract Increases:  $0

Approved Contract Decreases:  $ 0

Anticipated Completion Date: July 2021

Estimated Cost to Completion:   $14,658,155.85


PROGRESS:

November 6, 2019

Section I (West 130th Street to Abbey Road)

  • Complete except for new signals and signs.

    Section II (Abbey Road to 10655)

  • South side pavement in to intermediate course.
  • Currently working on the north side.
  • Expect curbs and asphalt by Thanksgiving. Once this section is complete it will be open to traffic.
  • Temporary zoned during the day will be set up to install the new aprons and sidewalks after the road is open.

    Section IIB (10655 to York Road)

  • Work to begin Spring 2020.

May  8, 2019

  • 95% of underground utilities (water and sewer lines) is complete.
  • Culvert work 80% complete.
  • Retaining wall by bus garage is 50% complete.
  • Phase I (West 130th Street to Abbey Road) work/widening began with stabilization, aggregate base and asphalt paving on the SOUTH side Phase I to be completed in May 2019.

April 10, 2019

  • Utilities: (new waterline and storm sewers) approximately 90% completed.
  • Southside of pavement Section I (W. 130th St., to Abbey Rd. approximately) was milled for excavation.
  • Excavation/Embankment for new road southside Section I to begin.
  • Once all new water taps complete (about 2 weeks), the plan is to open Section II (Abbey Rd., to York Rd.) completely until new widening work starts later in the year or next year.
January 16, 2019
  • Two-way traffic maintained on north side of pavement. 
  • Installation of new watermain is being performed. 
  • Work on new bridge/culvert has begun. 
  • Waterline work is from W. 130th Street to York Road.