Royalton Road From 130th Street to York Road in the City of North Royalton

  • Notice to Proceed: 11/1/2018
  • Start Date: 11/1/2018
  • Completion Date: 7/1/2021
  • Project Amount: $14,658,155.85
  • This Page Last Updated On: 3/4/2020

Contractor:
DiGioia-Suburban Excavating, LLC
(440) 237-1978

County Project Contacts: 
Ryan Maver (216) 556-3932
Todd Zima (440) 628-9229

Notice to Proceed: November 2018

Contract Award Amount:
  $14,658,155.85

Start Date:  November 2018  

Scheduled Completion Date:
July 2021 

Approved Contract Increases:  $0

Approved Contract Decreases:  $ 0

Anticipated Completion Date: July 2021

Estimated Cost to Completion:   $14,658,155.85


PROGRESS:

March 4, 2020

  • Currently working on Section from 11000 Royalton Road to York Road on the south side. Work includes pavement removal and cement stabilization. Anticipate short disruptions to drive access with this work.
  • Anticipate installing aggregate base, curbs and under drain after the stabilization is complete this week.
  • Aggregate base, under drains and curbs will be installed in the next 30 days.
  • All traffic is being maintained.

November 6, 2019

Section I (West 130th Street to Abbey Road)

  • Complete except for new signals and signs.

    Section II (Abbey Road to 10655)

  • South side pavement in to intermediate course.
  • Currently working on the north side.
  • Expect curbs and asphalt by Thanksgiving. Once this section is complete it will be open to traffic.
  • Temporary zoned during the day will be set up to install the new aprons and sidewalks after the road is open.

    Section IIB (10655 to York Road)

  • Work to begin Spring 2020.

May  8, 2019

  • 95% of underground utilities (water and sewer lines) is complete.
  • Culvert work 80% complete.
  • Retaining wall by bus garage is 50% complete.
  • Phase I (West 130th Street to Abbey Road) work/widening began with stabilization, aggregate base and asphalt paving on the SOUTH side Phase I to be completed in May 2019.

April 10, 2019

  • Utilities: (new waterline and storm sewers) approximately 90% completed.
  • Southside of pavement Section I (W. 130th St., to Abbey Rd. approximately) was milled for excavation.
  • Excavation/Embankment for new road southside Section I to begin.
  • Once all new water taps complete (about 2 weeks), the plan is to open Section II (Abbey Rd., to York Rd.) completely until new widening work starts later in the year or next year.
January 16, 2019
  • Two-way traffic maintained on north side of pavement. 
  • Installation of new watermain is being performed. 
  • Work on new bridge/culvert has begun. 
  • Waterline work is from W. 130th Street to York Road.