- Notice to Proceed: 6/16/2020
- Start Date: 6/16/2020
- Completion Date: 10/30/2020
- Project Amount: $13,457,744.18
- This Page Last Updated On: 12/7/2020
Contractor: County Project Contacts:
Chagrin Valley Paving Terry Cain (216) 633-0567
(216) 739-3170 Joe Charif (216) 701-1262
Notice to Proceed: June 2020 Contract Award Amount: $2,504,354.06
Start Date: June 2020 Approved Contract Increases: $0
Scheduled Completion Date: Approved Contract Decreases: $0
November 2020
Anticipated Completion Date: Estimated Cost to Completion: $0
November 2020
PROGRESS:
December 7, 2020
- Both sides of Ridge Road from Memphis Avenue to Clinton Road have been milled, chip sealed and paved with intermediate course asphalt.
- Castings have been adjusted to grade and concrete placed in the boxed-out areas on the left side.
- Topsoil was placed, as necessary.
- Placement of surface course asphalt has been completed.
- Concrete repairs have been completed from Clinton Avenue to Denison Ave, this area has been chip sealed and intermediate course asphalt has been place.
- Surface course asphalt will be placed this month.
November 6, 2020
- Both sides of Ridge Road from Memphis Avenue to Clinton Road have been milled, chip sealed and paved with intermediate course asphalt.
- Castings have been adjusted to grade and concrete placed in the boxed-out areas on the left side.
- Topsoil was placed, as necessary.
- Placement of surface course asphalt has been completed.
- Concrete repairs have been completed from Clinton Avenue to Denison Ave, this area has been chip sealed and intermediate course asphalt has been place.
- Surface course asphalt will be placed this month.
October 19, 2020
- Both sides of Ridge Road from Memphis Avenue to Clinton Road have been milled, chip sealed and paved with intermediate course asphalt.
- Castings have been adjusted to grade and concrete placed in the boxed-out areas on the left side.
- Topsoil was placed, as necessary.
- Placement of surface course asphalt has been completed.
- Concrete repairs and permanent paint markings will be completed in October.
September 10, 2020
-
Both sides of Ridge Road from Memphis Avenue to Clinton Road have been milled, chip sealed and paved with intermediate course asphalt.
- Castings have been adjusted to grade and concrete placed in the boxed-out areas on the left side.
- Topsoil was placed, as necessary.
- Surface course asphalt, full depth concrete and permanent paint markings will be completed this month.
August 5, 2020
-
Both sides of Ridge Road from Memphis Avenue to Clinton Road have been milled, chip sealed and paved with intermediate course asphalt.
-
Castings will be adjusted to grade and concrete placed in the boxed-out areas on the left side.
-
Topsoil will be placed, as necessary.
-
Surface course asphalt and permanent paint markings will be placed this month.