Noble Road Repair & Resurfacing

  • Notice to Proceed: 6/4/2012
  • Start Date: 6/11/2012
  • Completion Date: 10/15/2012
  • Project Amount: $1,314,468.45
  • This Page Last Updated On: 10/2/2012
County Project Contacts:
Darwin Merdes (216)348-4073
Ramzi Halasah (216)371-5490

Contractor:

C.A. Agresta
(216)) 382-2525

Progress:



October 2, 2012
  • The work within the 1.72 mile limits of this project include; Planing and resurfacing of the existing asphalt concrete wearing course; repair/and or removal of deteriorated concrete base and curb; adjustments or reconstruction to grade of various roadway castings.
  • Construction work along Noble Road will be performed in two separate construction sections; Section 1 ~ (The east side of the roadway will be reconstructed), followed in turn be Section 2 ~ (The west side of Noble Road).
  • Sections 1 and 2; began June 11, 2012; two-way traffic will be maintained at all times in one lane in each direction on the half width of the street not undergoing reconstruction.
  • Please use caution at all times when driving through the work zone.

Progress/Status September:

  • Performing street base repairs and re-establishing the roadway cross section on the west side of the roadway.
  • Adjusting and reconstructing to grade existing catch basins.
  • Placement of intermediate asphalt over repaired surfaces.
  • Replacing curb and sidewalk along the right-a-way.

Progress/Status October:

  • Casting will be adjusted to proposed surface course elevation.
  • Linear grading along with seeding and mulching will be performed to restore areas that were affected by the construction.
  • Surface course of asphalt will be placed along with pavement markings.

Please note the following:

  • Scheduled for October 11th and 12th traffic on Noble Road will be severely restricted due to the placement of the surface course asphalt. (City of East Cleveland has been notified-News Release will posted to the D.P.W. website).

June 20, 2012

  • The work within the 0.72 mile limits of this project include; Planing and resurfacing of the existing asphalt concrete wearing course; repair/and or removal of deteriorated concrete base and curb; adjustments or reconstruction to grade of various roadway castings.
  • Construction work along Noble Road will be performed in two separate construction sections; Section 1~ (The east side of the roadway will be reconstructed), followed in turn by Section 2~ (The west side of Noble Road).