Noble Road Resurfacing - Cleveland Hts.

  • Notice to Proceed: 4/1/2017
  • Start Date: 4/1/2017
  • Completion Date: 10/1/2017
  • Project Amount: $2,947,728.00
  • This Page Last Updated On: 7/7/2017

Contractor:
C.A. Agresta Construction Co.
(216) 382-2525

County Project Contacts:
Rich Orosz
(216) 600-5204

Darwin Merdes
(216) 348-4073

Approved Contract Increases:
$0

Approved Contract Decreases:
$0

July 7, 2017

 

PROGRESS:

  • Work continues along the western one half of Noble Road; two-way traffic is being maintained on the existing surfaces of the western one half of the road with one lane in each direction. All intersections are currently open to traffic.
  • Placement of intermediate course asphalt on eastern one half of Noble Road including 18 various intersection.
  • Removing and inspecting existing roadway castings; rebuilding and adjusting to grade various manhole, catch basin, and water valves. The old roadway castings are being replaced with new iron as required.
  • Removal and replacement of existing sandstone curbs, ADA ramps, and concrete drive aprons beginning at Monticello and working north to Greyton Road.

    Progress

    June 15, 2017
  • Work continues along the western one half of Noble Road; two-way traffic is being maintained on the existing surfaces of the western one half of the road with one lane in each direction. All intersections are currently open to traffic.
  • Weather permitting on 6/19/17 I Switch to Phase II
    Two way traffic will be moved to the western one half of Noble road as work will begin on the eastern one half of the roadway and intersections.
  • Carron to begin the process of removing 3” of existing asphalt wearing course material from Warrensville Center Road to Greyton Road as well as the following intersections; Ardmore, Rosemond, Navahoe, Elmwood, Bluestone, Orchard, Delmore, Roanake, Oxford, Quilliams, Nobleshire, Vineshire, Yellowstone, Clearence, Medford, Lecona, Woodview, and Greyton.
  • With the completion of asphalt wearing course removal, the existing base pavement will be inspected; areas in need of full depth or partial repairs will be identified and marked for removal and replacement.
  • Agresta Construction will continue removing and inspecting existing roadway castings; rebuilding and adjusting to grade various manhole, catch basin, and water valve castings.
  • The old roadway castings are being replaced with new iron as required. This work will occur on Noble road between Mayfield Road and Warrensville Center Road.