You are here: Home > Projects & Programs > Construction Updates 

Noble Road Resurfacing - Cleveland Hts.

  • Notice to Proceed: 4/1/2017
  • Start Date: 4/1/2017
  • Completion Date: 10/1/2017
  • Project Amount: $2,947,728.00
  • This Page Last Updated On: 10/10/2017

Contractor:
C.A. Agresta Construction Co.
(216) 382-2525

County Project Contacts:
Rich Orosz
(216) 600-5204

Darwin Merdes
(216) 348-4073

Approved Contract Increases:
$0

Approved Contract Decreases:
$0 

PROGRESS:

October 10, 2017

  • Surface course paving was completed on 9/26/17. All lanes of traffic are now open from curb to curb including intersections along Noble Road.
  • Work expected in the upcoming weeks will include;
  • General clean-up final landscaping and restorations.
  • Complete final paint markings; including long line epoxy striping in addition to short line thermoplastic placement.
  • Walk through inspection and punch list items.
  • Full width surface course asphalt paving of Noble Road from Greyton to Warrensville Road including all intersections scheduled for second week in October (weather permitting), following by permeant striping and re-opening of roadway.
  • Various punch list activities.

September 1, 2017

Work continues along the eastern one half of Noble Road; two-way traffic is being maintained on the newly placed intermediate asphalt surfaces of the western one half of the road with one lane in each direction.

  • Complete construction of new aprons, ADA ramps and sidewalks in the section of Noble Road between Greyton Road and Ardmore Road.
  • Complete the adjustment various manhole, catch basin, and water service castings using new iron casting replacement as necessary.
  • General clean-up; grading of eastern material within tree lawn areas followed by placement of top soil/and seeding and mulching.
  • Full width surface asphalt paving f Noble Road from Greyton Road to Warrensville Road including all intersections scheduled for second week of September (weather permitting), followed by permeant striping and re-opening of roadway.
  • Various punch list activities.

August 3, 2017

  • Work continues along the eastern one half of Noble Road; two-way traffic is being maintained on the newly placed intermediate asphalt surfaces of the western one half of the road with one lane in each direction. All intersections are currently open to traffic.
  • Beginning at Greyton Road and working to the south; Removal of existing sandstone curb followed by construction of new type 6 curbing, aprons, and ADA ramps/walks.
  • Reconstruction/cleaning and setting of existing catch basin structures, new iron castings will be used.
  • General clean-up of tree lawn areas followed by placement of top soil, seeding and mulching.

    July 7, 2017
  • Work continues along the western one half of Noble Road; two-way traffic is being maintained on the existing surfaces of the western one half of the road with one lane in each direction. All intersections are currently open to traffic.
  • Placement of intermediate course asphalt on eastern one half of Noble Road including 18 various intersection.
  • Removing and inspecting existing roadway castings; rebuilding and adjusting to grade various manhole, catch basin, and water valves. The old roadway castings are being replaced with new iron as required.
  • Removal and replacement of existing sandstone curbs, ADA ramps, and concrete drive aprons beginning at Monticello and working north to Greyton Road.

    Progress

    June 15, 2017
  • Work continues along the western one half of Noble Road; two-way traffic is being maintained on the existing surfaces of the western one half of the road with one lane in each direction. All intersections are currently open to traffic.
  • Weather permitting on 6/19/17 I Switch to Phase II
    Two way traffic will be moved to the western one half of Noble road as work will begin on the eastern one half of the roadway and intersections.
  • Carron to begin the process of removing 3” of existing asphalt wearing course material from Warrensville Center Road to Greyton Road as well as the following intersections; Ardmore, Rosemond, Navahoe, Elmwood, Bluestone, Orchard, Delmore, Roanake, Oxford, Quilliams, Nobleshire, Vineshire, Yellowstone, Clearence, Medford, Lecona, Woodview, and Greyton.
  • With the completion of asphalt wearing course removal, the existing base pavement will be inspected; areas in need of full depth or partial repairs will be identified and marked for removal and replacement.
  • Agresta Construction will continue removing and inspecting existing roadway castings; rebuilding and adjusting to grade various manhole, catch basin, and water valve castings.
  • The old roadway castings are being replaced with new iron as required. This work will occur on Noble road between Mayfield Road and Warrensville Center Road.