Abbey Road Bridge - N. Royalton /Harris Rd Bridge-Broadview Hts., Bridge Box Beam Program Part 1

  • Notice to Proceed: 4/1/2018
  • Start Date: 4/1/2018
  • Completion Date: 10/1/2018
  • Project Amount: $1,792,814.14
  • This Page Last Updated On: 12/6/2018
Date: June 11, 2018

Contractor: Global Outdoor Solutions LLC dba Fourtounis Group

County Project Contacts: 
Brian Vigh-(216) 301-9010
Joe Charif (216) 701-1262

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
October 2018

Contract Award Amount: $1,033,235.00

Estimated Cost to Completion:
$631,399.00

Scheduled Completion Date:  October, 2018

Anticipated Completion Date:  October, 2018

PROGRESS:

December 6, 2018

Current Work:

Harris Road:

  • Harris Road Bridge 01.61 is open to traffic, however a few plan items remain to be completed.
  • Many of these are temperature related. Work will resume in the spring.

Abbey Road:

  • Abbey Road Bridge 02.35 is open to traffic.
November 9, 2018
  • Harris Road:  
    • Harris Road Bridge 01.61 is completely closed to traffic. Detour is in affect as per plan.
    • Installation of new box beams on Harris road  
    • Poured approach slabs, bridge deck, and sidewalk on Harris Road 
  • Abbey Road: 
    • Abbey Road Bridge 02.35 is open to traffic.  
    • Forming parapet and wingwall repair on Abbey Road  
    • Seeding and mulching on Abbey Road.

October 5, 2018


Current Zone:
  • Abbey Road Bridge 02.35 is open to traffic.  
  • Harris Road Bridge 01.61 is complexly closed to traffic. Detour is in affect as per plan. 
Current Work:
  • Removal of existing box beam bridge on Harris Road. 
  • Removal of existing abutment walls on Harris Road. 
  • Poured proposed abutment walls on Harris Road 
  • Waterproofing and backfilling of Harris Road in preparation for new box beams 
  • Staining of parapet walls on Abbey Road.

September 6, 2018

Current Zone:
  • Abbey Road Bridge 02.35 is open to traffic.
  • Harris Road Bridge 01.61 is complexly closed to traffic. Detour is in affect as per plan.
Current Work:
  • Poured parapet walls on Abbey Road Bridge.
  • Installed roadway pavement on Abbey Road.
  • Installed guardrail and pavement striping on Abbey Road.
  • Continued demolition of Harris Road Bridge.
Progress:

June 12, 2018
  • Current Zone
  • Abbey Road Bridge 02.35 is completely closed to traffic. Detour is affect as per plan.
  • Harris Road Bridge construction will begin in July.

Current Work:

  • Removal of existing roadway deck
  • Removal of existing box beam bridge
  • Excavation down to top of footing rear/forward abutments and saw cut to plan elevation for proposed work.