Memphis Road Replacement

  • Notice to Proceed: 3/1/2020
  • Start Date: 3/1/2020
  • Completion Date: 7/1/2023
  • Project Amount: $5,853,453.30
  • This Page Last Updated On: 11/16/2020

Contractor:
Independence Excavating, Inc.: 440-891-1444

County Project Contacts:
Joe Charif: 440-701-1262
Bill Nugent

Approved Contract Increases:
$0

Approved Contract Decreases:
$0


PROGRESS:

Work Completed:

  • Closed North side (left) curb lane and sidewalk.
  • Removed guardrail on north side.
  • Performed clearing and grubbing on the north and south side of the structure.
  • Installed perimeter filter fabric fence and installed inlet fabric protection as per the approved stormwater pollution prevention plan.
  • Excavated access road to boring pit.

     

    Work to be Performed:        

  • Set-up and mobilize equipment for boring under CSX railroad.
  • Perform boring and jack 54” steel casing for 36” waterline.
  • Begin excavating and installing new 36” ductile iron waterline.