Mastick Road Bridge Replacement

  • Notice to Proceed: 3/1/2020
  • Start Date: 3/1/2020
  • Completion Date: 7/1/2021
  • Project Amount: $4,115,506.66
  • This Page Last Updated On: 10/14/2020

Contractor:
Kokosing Construction Company, Inc.: 440-891-1444

County Project Contacts:
Joe Charif: 440-701-1262
Bill Nugent

Approved Contract Increases:
$0

Approved Contract Decreases:
$0


PROGRESS:

October 14, 2010

Mastic Road between Eaton Road and Valley Parkway is closed. 


Work Completed:

• Install new epoxy coated reinforcing steel for the structure’s deck Phase I and Phase II.

          • Place QC2 concrete for superstructure, as per plan, Phase I.

Maintain water cure for deck.

• Install new epoxy coated reinforcing steel for parapet wall.
• Form and install new epoxy coated reinforcing steel for the forward approach slab.
• Place concrete and maintain water cure for the forward approach slab
• Excavate and form pressure relief joints for the rear and forward pavement areas. 

 

Work to be Performed: 

Place QC2 concrete for superstructure, as per plan, Phase II.

Maintain water cure for deck. 

August 5, 2020

  • Mastic Road between Eaton Road and Valley Parkway is closed

    Work Completed:

  • Removal of guardrail on the east side of the roadway.
  • Clearing and grubbing within the construction limits.
  • Drilling shafts and then placing concrete for reinforced foundations for piers.
  • Drilling shafts and placing concrete soldier piles for hillside wall.
  • Work to be Performed:
  • Continue the installation of foundations and pier caps.
  • Continue drilling shafts to install concrete solider pier for walls.
  • Begin removal of structure.

 July 10, 2020

  • Form forward abutment wall and install new epoxy coated reinforcing steel.
  • Place concrete for forward abutment wall.
  • Install porous backfill and drainage along forward abutment.
  • Install precast concrete panels for forward wingwall.
  • Continue demolition of structure and removal of material from the project.
  • Install falsework and decking for the new structure between piers.

    Upcoming Work:

  • Finish demolition of the structure and removal of material.
  • Remove rear approach slab.
  • Install rear wingwall precast concrete panels.
  • Remove existing rear abutment.
  • Form and install reinforcing steel for the rear abutment.
  • Continue the installation of falsework and decking.

June 3, 2020

  • Soldiers piles drilled with piles set in concrete foundations for the north walls 1 & 2.
  • Soldier piles drilled with piles set in concrete foundations for the forward right wingwall and the rear right wingwall.
  • Remove existing north side parapet wall.
  • Concrete panels installed for lagging on north walls 1 and 2.
  • Removal of forward approach slab and the forward abutment wall.
  • Form forward abutment wall and install new epoxy coated reinforcing steel.

    Upcoming Work:
  • Complete forming forward abutment wall and place concrete for the forward abutment wall.
  • Continue demolition of the structure.
  • Repair existing pier caps.
  • Begin falsework for the decking structure.


April 7, 2020
  • Mastic Road between Eaton Road and Valley Parkway is closed.

    Work Completed:
  • Removal of guardrail on the east side of the roadway.
  • Clearing and grubbing within the construction limits.
  • Drilling shafts and then placing concrete for reinforced foundations for piers.
  • Drilling shafts and placing concrete soldier piles for hillside wall.

    Work to be Performed:
  • Continue the installation of foundations and pier caps.
  • Continue drilling shafts to install concrete solider pier for walls.
  • Begin removal of structure.