  • Notice to Proceed: 3/1/2020
  • Start Date: 3/1/2020
  • Completion Date: 7/1/2021
  • Project Amount: $4,115,506.66
  • This Page Last Updated On: 4/7/2020

Contractor:
Kokosing Construction Company, Inc.: 440-891-1444

County Project Contacts:
Joe Charif: 440-701-1262
Bill Nugent

Approved Contract Increases:
$0

Approved Contract Decreases:
$0


PROGRESS:

April 7, 2020

  • Mastic Road between Eaton Road and Valley Parkway is closed.

    Work Completed:
  • Removal of guardrail on the east side of the roadway.
  • Clearing and grubbing within the construction limits.
  • Drilling shafts and then placing concrete for reinforced foundations for piers.
  • Drilling shafts and placing concrete soldier piles for hillside wall.

    Work to be Performed:
  • Continue the installation of foundations and pier caps.
  • Continue drilling shafts to install concrete solider pier for walls.
  • Begin removal of structure.