You are here: Home > Projects & Programs > Construction Updates 

Highland Road Rehabilitation of Bridges 156,157,158, & 226 - Euclid

  • Notice to Proceed: 2/5/2018
  • Start Date: 12/1/2017
  • Completion Date: 5/31/2018
  • Project Amount: $14,891,604.32
  • This Page Last Updated On: 5/7/2018

Date: May 7, 2018

Contractor: Union Industrial Contractors

County Project Contacts:  Ramzi Halasah   216-348-3836

Notice to Proceed: December 2017

Contract Award Amount:
  $14,891,604.32

Start Date: December 2017

Approved Contract Increases:  $0

Scheduled Completion Date: May 2020

Approved Contract Decreases:  $0

Anticipated Completion Date: May 2020

Estimated Cost to Completion:  
 $14,891,604.32

Progress For:

Operations Group 2-Turney Road (Hathaway Rd. to Garfield Height East Corp. Line) - Garfield Heights /
Eastland /Fowles Rd -Berea South Corp. Line to Bagley Rd.-City of Berea

Progress:

May 7, 2018
  • Bridge 157, Pier 2 has been formed and poured. 
  • Steel plates have been placed and the location of beams have been marked on the bridge deck for construction traffic to be flagged. 
  • Temporary sanitary line was activated on bridge 156.

    Maintenance of Traffic: 
  • Contractor’s hours have been changed to four 10-hour days.


  • Work Continues bridges 156 and 157,
  • Access roads have been established.
  • Guardrail has been removed and bridge deck saw cutting has begun.          

Maintenance of Traffic:

  • Traffic is being maintained one lane direction.
  • In the next few weeks the actual demolition will begin.