You are here:
Home > Projects & Programs > Construction Updates
Highland Road Rehabilitation of Bridges 156,157,158, & 226 - Euclid
- Notice to Proceed: 2/5/2018
- Start Date: 12/1/2017
- Completion Date: 5/31/2018
- Project Amount: $14,891,604.32
- This Page Last Updated On: 2/14/2019
Date: May 7, 2018
Contractor: Union Industrial Contractors
County Project Contacts: Ramzi Halasah 216-795-5477
Notice to Proceed: December 2017
Contract Award Amount: $14,891,604.32
Start Date: December 2017
Approved Contract Increases: $0
Scheduled Completion Date: May 2020
Approved Contract Decreases: $0
Anticipated Completion Date: May 2020
Estimated Cost to Completion: $14,891,604.32
Progress:
February 14, 2019
- Work on the east side of bridges #156 and #157 has been completed.
- Contractor is now beginning work on the west side of these two bridges.
- Work has begun on the east side of bridges #158 and #226.
Maintenance of Traffic:
- A new traffic pattern was implemented in early January to continue the maintenance
Traffic with one lane in each direction while addressing the new work zones on
all 4 bridges. Portable message boards, concrete barriers and barrels are being used
to direct motorist.
May 7, 2018
- Bridge 157, Pier 2 has been formed and poured.
- Steel plates have been placed and the location of beams have been marked on the bridge deck for construction traffic to be flagged.
- Temporary sanitary line was activated on bridge 156.
Maintenance of Traffic:
- Contractor’s hours have been changed to four 10-hour days.
-
Work Continues bridges 156 and 157,
-
Access roads have been established.
-
Guardrail has been removed and bridge deck saw cutting has begun.
Maintenance of Traffic: