Greenbrooke Retention Basin Olmsted Township
- Notice to Proceed: 3/16/2012
- Start Date: 3/26/2011
- Completion Date: 4/30/2012
- Project Amount: $160,036.00
- This Page Last Updated On: 8/3/2012
- Contractor:
Fabrizi Trucking & Paving Co. 440-234-1284
- County Project Contacts:
Todd Zima 216-348-3800
Mike Tworzydlo 216-348-3895
Field Office 440-235-4718
- Approved Contract Increases: $0
- Approved Contract Decreases: $0
PROGRESS
August 3, 2012
- All contract work is complete.
June 20, 2012
- All contract work is complete.
- Final walk through will be scheduled
- Some touchup landscaping might be required.
April 13, 2012
- Work was delayed due to the fact that the basin was full of water and needed to drain somewhat in order to get equipment in.
- Clearing of the basin has been completed.
- In May, Fabrizi Trucking and Paving Company will complete grading and
- seeding to complete the project.

Greenbrook 1 |
|

Greenbrook 2
|