Greenbrooke Retention Basin Olmsted Township

  • Notice to Proceed: 3/16/2012
  • Start Date: 3/26/2011
  • Completion Date: 4/30/2012
  • Project Amount: $160,036.00
  • This Page Last Updated On: 8/3/2012
  • Contractor:
    Fabrizi Trucking & Paving Co.  440-234-1284
  • County Project Contacts:
    Todd Zima 216-348-3800
    Mike Tworzydlo 216-348-3895
    Field Office  440-235-4718
  • Approved Contract Increases: $0
  • Approved Contract Decreases: $0

PROGRESS

August 3, 2012

  • All contract work is complete.

June 20, 2012

  • All contract work is complete.
  • Final walk through will be scheduled
  • Some touchup landscaping might be required.

April 13, 2012

  • Work was delayed due to the fact that the basin was full of water and needed to drain somewhat in order to get equipment in.
  • Clearing of the basin has been completed.
  • In May, Fabrizi Trucking and Paving Company will complete grading and
  • seeding to complete the project.

 

 