Green Rd Repair & Resurfacing
- Notice to Proceed: 6/4/2012
- Start Date: 6/11/2012
- Completion Date: 11/16/2014
- Project Amount: $2,213,811.02
- This Page Last Updated On: 10/3/2012
CONSTRUCTION PROJECT UPDATE
Green Road
Repair and Resurfacing from Fairmount to Chagrin Blvd. In the Cities of Shaker Heights & Beachwood
County Project Contacts:
Mike Tworzydlo (216) 348‐3895
Rich Orosz (216) 342‐4241
Contractor:
Burton Scot, LLC
Phone: (440) 564‐1011
PROGRESS:
- Sub‐contractor continuing full depth repairs in designated areas in Section‐2.
- Curb removal.
- New 24” storm sewer installation.
- Drive apron removal.
- Sidewalk and curb ramp removed.
- All work remains in progress in the City of Beachwood.
- Current Traffic Zone:
- One‐way northbound traffic will be maintained from Chagrin Blvd. to S.Woodland in theCity of Beachwood. (Phase 2 of operation).
PROGRESS:
- Contractor completed installation of surface course type‐1 asphalt in Section‐1 of Green Rd.
- Temporary striping placed in mainline of Green Road.
- Traffic & signal change, opening Section‐1 to two‐way traffic and closing one lane in Section‐2.
- Work began in Section‐2 of Green Road, pavement planning of existing asphalt.
- Sub‐contractor began full depth repairs in designated areas in Section‐2.
- Patching of concrete type A and additional sidewalk repairs on RTA bridge deck continues.
- Current Traffic Zone:
- One‐way northbound traffic will be maintained from Chagrin Blvd. to S.Woodland in the City of Beachwood. (Phase 2 of operation).