All County buildings are currently closed to the public. Please visit our Online services page for resources and information. Cuyahoga County Justice Center, Juvenile Justice Center, and Courthouse remain open for essential functions.

You are here: Home > Projects & Programs > Construction Updates 

Future Amazon Site Perimeter Roads - City of Euclid

  • Notice to Proceed: 10/1/2018
  • Start Date: 12/1/2018
  • Completion Date: 7/1/2019
  • Project Amount: $1,354.515.80
  • This Page Last Updated On: 1/14/2020

Contractor:
Karvo Paving Comapnies, Inc.
(330) 929-9616

County Project Contacts: 
Ryan Maver   (216) 556-3932
Michael Cotter (216) 280-8757

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
July 2019

Estimated Cost to Completion: $1,354,515.80

PROGRESS

January 14, 2020

Work Expected in the upcoming weeks will include:

  • Installation of signal poles and signal equipment
  • Installation of all required cables
  • Placing new signals into operation
  • Timing of signals and signal analysis

November 6, 2019

Work Expected in the upcoming weeks will include
:

 

  • Delivery and installation of signal poles and signal equipment


May 8, 2019

Work Expected in the upcoming weeks will include:

  • Surface course asphalt in various areas.
  • Widening of radius on Lakeland Boulevard and Babbitt Road.
  • Boring of conduit under roadway.

February 6, 2019

Work Expected in the upcoming weeks will include:

  • Road widening of Babbitt Road.
  • Traffic Signal foundations approved.
  • Traffic signal poles ordered.
  • Underground traffic signal work.
January 16, 2019

Work Expected in the upcoming weeks will include: 
  • Road widening of Babbitt Road. 
  • Temporary traffic signals placed and removal of existing signals. 
  • Traffic signal foundations placed and poured.