You are here: Home > Projects & Programs > Construction Updates 

Future Amazon Site Perimeter Roads - City of Euclid

  • Notice to Proceed: 10/1/2018
  • Start Date: 12/1/2018
  • Completion Date: 7/1/2019
  • Project Amount: $1,354.515.80
  • This Page Last Updated On: 5/8/2019
Contractor:
Karvo Paving Comapnies, Inc.
(330) 929-9616

County Project Contacts: 
Ryan Maver   (216) 556-3932
Michael Cotter (216) 280-8757

Approved Contract Increases: $0

Approved Contract Decreases: $0

Anticipated Completion Date:
July 2019

Estimated Cost to Completion: $1,354,515.80

PROGRESS

May 8, 2019

Work Expected in the upcoming weeks will include:

  • Surface course asphalt in various areas.
  • Widening of radius on Lakeland Boulevard and Babbitt Road.
  • Boring of conduit under roadway.

February 6, 2019

Work Expected in the upcoming weeks will include:

  • Road widening of Babbitt Road.
  • Traffic Signal foundations approved.
  • Traffic signal poles ordered.
  • Underground traffic signal work.
January 16, 2019

Work Expected in the upcoming weeks will include: 
  • Road widening of Babbitt Road. 
  • Temporary traffic signals placed and removal of existing signals. 
  • Traffic signal foundations placed and poured.