- Notice to Proceed: 5/1/2020
- Start Date: 5/1/2020
- Completion Date: 11/2/2020
- Project Amount: $3,620,427.30
- This Page Last Updated On: 12/4/2020
Contractor: County Project Contacts:
The Vallejo Company Ryan Maver (216) 348-3819
(216) 741-3933 Brian Vigh (216) 301-9010
Notice to Proceed: May 2020 Contract Award Amount: $3,991,132.48
Start Date: May 2020 Approved Contract Increases: $0
Scheduled Completion Date: May 2020 Approved Contract Decreases: $0
Anticipated Completion Date: November 2020 Estimated Cost to Complete: $3,620,427.30
PROGRESS:
December 4, 2020
- Roadway is completely open to traffic in both north and southbound directions.
- All signage on the construction site has been installed.
- Much of the final striping has also been completed.
November 6, 2020
- Work is being done to finalize all striping within the job limits.
- All other work items have been completed.
October 14, 2020
- All traffic reconfigurations were completed including the roundabout at MLK and the turning lanes at Corlett Ave.
- Surface asphalt course has been placed across the entire jobsite.
- Pavement sawing at control joints is being started.
- Topsoil and seed are being placed across the entire job site to repair any damaged areas.
Maintenance of Traffic:
- Traffic is still controlled by construction barrels and cones, until permanent striping is placed.
- Traffic is being maintained in both north and south directions.
September 10, 2020
- Work is being done to perform casting replacement and adjustments between Union and Harvard Avenue in both directions.
- Work is continuing for the construction of the roundabout at the Farrington and E. 116th Avenue intersection.
- All sewer work and roadway base grading has been completed.
- Work is currently being setup to complete roadway pavement.
Maintenance of Traffic:
- Northbound traffic is closed at E. 116th and Corlett Avenue, detour is in effect.
- Southbound traffic is partially reopened and is utilizing newly constructed roundabout at E. 116th Street and MLK.
- One-way traffic is utilized in both directions.
August 5, 2020
- Most of the intersection re configurations at MLK and Corlett Avenue have been completed where each have been brought back to intermediate surface asphalt.
- Work is being done to perform castings replacement and adjustments between MLK and Harvard Avenue in both directions.
- Work is beginning to construct the other half of the proposed roundabout at E. 116th and MLK in the northbound lanes.
Maintenance of Traffic:
- Northbound traffic is closed at E. 116th and Corlett Avenue, detour is in effect.
- Southbound traffic is partially reopened and is utilizing newly constructed roundabout at E. 116th Street and MLK.
- One-way traffic is utilized in both directions.
July 10, 2020
- Roadway pavement has been removed at the intersection of MLK Avenue and E. 116th Street to reconfigure the intersection into a roundabout.
- This will include removal of roadway, sub-base, walk, curb and drainage facilities.
Maintenance of Traffic:
- Southbound traffic is closed at E. 116th Street and MLK Avenue; detour is in effect.
- Northbound traffic tapers down to one lane at the intersection of E. 116th St., and MLK Ave.
- This is all due to construction to reconfigure the E. 116th St., and MLK Ave. intersection.