E. 105th Street/MLK Improvement

  • Notice to Proceed: 4/18/2011
  • Start Date: 10/22/2012
  • Completion Date: 8/29/2014
  • Project Amount: $7,210,946.75
  • This Page Last Updated On: 7/2/2014
  • Contractor:
    Terrace Construction Company
    Phone: (216) 739‐3170 
  • Approved Contract Increases: $164,479.18
  • Approved Contract Decreases: $25,929.00
  • Estimated Cost to Completion:  $4,500,000.00

Progress

July 2, 2014

Current Zone:
  • Phase 1 work zone in place. North and south bound traffic on E105TH is now two-way (one lane each direction) in the north bound lanes.
  • Mt. Sinai closed. Detour in place per plan.
  • Westbound lanes on MLK, west of E105TH closed. Two-way traffic maintained in east bound lanes.

Current Work:

  • Terrace Construction continues construction of the west side of E105TH/MLK, including new sidewalks and landscape restoration.
  • Terrace Construction continues construction of proposed pedestrian bridge behind the Cancer Survivors Monument and proposed landscape restoration.

May 8, 2014

Description:

Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive.  This will include pavement widening, geometric realignment, signal work, and landscaping.

   Current Zone
:
  • Phase 1 work zone in place. North and south bound traffic on E. 105th is now two-way (one-lane each direction) in the north bound lanes.
  • Mt. Sinai closed. Detour in place per plan.
  • Westbound lanes on MLK, west of E. 105th Street closed.
  • Two-way traffic maintained in eastbound lanes. 
   Current Work:

  • Terrace Construction continues construction of proposed pedestrian bridge behind the Cancer Survivors Monument
April 2, 2014

Current Work:
  • Terrace Construction has begun excavation/embankment construction on the west side of E. 105th.
  • Terrace Construction continues construction of proposed pedestrian bridge behind the Cancer Survivors Monument.


February 3, 2014

Description:
Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal work, and landscaping.

Current Zone:
• Phase 1 work zone in place. North and south bound traffic on E. 105th is now two-way (one-lane each direction) in the north bound lanes.
• Mt. Sinai closed. Detour in place per plan.
• Westbound lanes on MLK, west of E. 105th Street closed.
• Two-way traffic maintained in eastbound lanes.

Current Work:
• Cleveland Public Power continues work to relocate electrical utilities.
• Terrace Construction shut down for the winter.



January 2, 2014

Description:
Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal
work, and landscaping.

Current Zone:

• Phase 1 work zone in place. North and south bound traffic on E. 105th is now two-way (one-lane each direction) in the north bound lanes.
• Mt. Sinai closed. Detour in place per plan.
• Westbound lanes on MLK, west of E. 105th Street closed.
• Two-way traffic maintained in eastbound lanes.

Current Work:

• Cleveland Public Power continues work to relocate electrical utilities.
• Terrace Construction shut down for the winter.


December 3, 2013

Description:

Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal
work, and landscaping.

Current Zone:
  • Phase 1 work zone in place. North and south bound traffic on E. 105th is now two-way (one-lane  each direction) in the north bound lanes.
  • Mt. Sinai closed. Detour in place per plan.
  • Westbound lanes on MLK, west of E. 105th Street closed.
  • Two-way traffic maintained in eastbound lanes.
  • Current Work:
  • Cleveland Public Power continues work to relocate electrical utilities.
  • Terrace Construction shut down for the winter.

November 13, 2013
Current Zone:
  • Phase 1 work zone in place. North and south bound traffic on E. 105th is now two-way (one-lane each direction) in the north bound lanes.
  • Mt. Sinai closed. Detour in place per plan.
  • West bound lanes on MLK, west of E. 105th Street closed.
  • Two-way traffic maintained in east bound lanes.

Current Work:
  • Cleveland Public Power continues to install new power cables in new conduit
  • Completion of concrete base pavement and asphalt pavement on MLK, west of E. 105th and on Mt. Sinai.
  •  Removal and reconstruction of the west side of E. 105th.
  • Completion of 10’ and 6’ asphalt paths on MLK, east of E. 105th.
  • Completion of relocation of the General Stefanik Monument in Slovak Peace Garden.

October 3, 2013

Current Zone:
  • Phase 1 work zone in place. North and south bound traffic on E. 105th is now two-way (one-lane each direction) in the north bound lanes.
  • Mt. Sinai closed. Detour in place per plan.
  • West bound lanes on MLK, west of E. 105th Street closed.
  • Two-way traffic maintained in east bound lanes.
Current Work:
  • Completion of concrete base pavement and asphalt pavement on MLK, west of E. 105th and on Mt. Sinai.
  • Cleveland Public Power continues to install new power cables in new conduit.
  • Removal and reconstruction of the west side of E. 105th.

August 30, 2013

  • Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive.  This will include pavement widening, geometric realignment, signal work, and landscaping.
  • Current Zone:
    • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two-way traffic maintained in northbound lanes in this area.
    • Mt. Sinai closed. Detour in place per plan.
    • West bound lanes on MLK, west of E. 105th Street closed.
    • Two-way traffic maintained in east bound lanes.
  • Current Work:
    • Cleveland Public Power continues to install new power cables in new conduit.
    • Installation of proposed water work on E. 105th Street
    • Removal and reconstruction of the west bound section of MLK, west of E. 105th.

July 2, 2013

  • Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal work, and landscaping.
  • Current Zone:
    • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two-way traffic maintained in northbound lanes in this area.
    • Mt. Sinai closed. Detour in place per plan.
  • Current Work:
    • Cleveland Public Power continues to install new power cables in new conduit.
    • Installation of proposed roadway, street lighting foundations, conduit, and pull boxes, and proposed sidewalk on Mt. Sinai.
    • Relocation of the General Stefanik Monument. (Statute portion removed).
    • Installation of proposed storm sewers on the west side of E. 105th Street.

June 1, 2013

Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal
work, and landscaping.

Current Zone:
  • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two-way traffic maintained in northbound lanes in this area.
  • Mt. Sinai closed. Detour in place per plan.
Current Work:
  • Cleveland Public Power subcontractor, Cook Paving continues to install power cables in new conduit.
  • Terrace Construction continues work to install proposed roadway on Mt. Sinai.
  • Construction Company is working to relocate General Stefanik Monument to Peace Gardens.

May 6, 2013

Description:

Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal
work, and landscaping.

Current Zone:

  • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two-way traffic maintained in northbound lanes in this area.
  • Mt. Sinai closed. Detour in place per plan.

Current Work:

  • Cleveland Public Power subcontractor, Cook Paving continues work install proposed cast in place manholes for CPP conduit/pull boxes for street lighting.
  • Terrace Construction is installing proposed drainage work on St. Sinai.
  • Construction Company is working to relocate General Stefanik Monument to Peace Gardens.
April 2, 2013
  • Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. This will include pavement widening, geometric realignment, signal work, and landscaping.
  • Current Zone:
    • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two-way traffic maintained in northbound lanes in this area.
    • Mt. Sinai closed. Detour in place per plan.
  • Current Work:
    • Cleveland Public Power subcontractor, Cook Paving continues work install proposed cast in place manholes for CPP on Mt. Sinai.
    • Terrace Construction began installation of proposed CPP electrical conduit and pre cast manholes.
    • Proposed pedestrian bridge abutment walls have been completed.
  • Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. Including pavement widening, geometric realignment, signal work, and landscaping.

Current Zone:

  • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two‐way traffic maintained in northbound lanes in this area.
  • Mt. Sinai closed. Detour in place per plan.

Current Work:

  • Cleveland Public Power subcontractor Cook Paving continues work install proposed cast in place manholes for CPP on Mt. Sinai.
  • Terrace Construction is continuing removal of existing pavement on Mt.Sinai.
  • Terrace Construction began installation of proposed CPP electrical conduit and pre cast manhole on the west side of E. 105th, south of Mt. Sinai.

Progress

  • Progress Description: Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. Including pavement widening, geometric realignment, signal work, and landscaping.
  • Current Zone:
  • Southbound lanes on E. 105th, south of Mount Sinai, closed. Two‐way traffic maintained in northbound lanes in this area.
  • Current Work:
  • Dominion East Ohio subcontractor continued relocation of gas mains on East 105th St. and MLK Drive.
  • Cleveland Public Power subcontractor continues work to install electrical conduit on the west side of E. 105th, south of Mount Sinai STA 90+80 LT to 91+30 LT.
  • Terrace Construction Company continues excavation work on the west side of E. 105th, south of Mount Sinai.

Progress

December 27, 2012

  • Progress Description: Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. Including pavement widening, geometric realignment, signal work, and landscaping.
  • Current Zone: Southbound lanes on E. 105th, south of Mount Sinai, closed. Two‐way traffic
    maintained in northbound lanes in this area.
  • Current Work: Dominion East Ohio subcontractor continued relocation of gas mains on East
    105th St. and MLK Drive.
  • Cleveland Public Power subcontractor continues work to install electrical conduit on the west side of E. 105th, south of Mount Sinai STA 90+80 LT to 91+30 LT.

December  4, 2012

  • Progress Description; Modification to the existing roadway network that includes MLK Drive,
  • East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. Including pavement widening, geometric realignment, signal work, and landscaping.

    Current Zone:
    • Two‐way traffic maintained throughout project. Curb lane closed for CPP work, southbound E. 105th, south of MLK.
    • Dominion East Ohio relocation of gas mains on East 105th St. and MLK Drive.
    • Cleveland Public Power demolition of existing manhole STA 154+10
    • Terrace Construction completed majority of clearing and grubbing, began work for proposed pedestrian bridge foundation along with excavation of Mt. Sinai hill.

October 22, 2012

Progress Description
  • Modification to the existing roadway network that includes MLK Drive, East 105th Street, Mount Sinai, East Boulevard, and Jepthra Drive. Including pavement widening, geometric realignment, signal work, and landscaping.
Work Expected to Begin: October 22, 2012
  • Prior to Terrace Construction beginning the project work, Dominion East Ohio Gas and Cleveland Public Power will begin utility work. Work for both will begin the week of October 22nd. Detours may be in place for the East Ohio Gas main relocation. This work is required to be done prior to the project beginning and is not administered by the County.
  • Dominion East Ohio relocation of gas main on East 105th St. and MLK Drive.  
  • Cleveland Public Power demolition of existing manhole STA 154+10.
  • Terrace Construction to begin work on clearing and grubbing on 11-5-12.
October 1, 2012
  • Two-way traffic will be maintained at all times through the use of work zone traffic signals. MLK (West of E. 105th St.)
  • Two-way traffic will be maintained at all times through the use of work zone traffic signals. MLK Drive (East of E. 105th St.)
  • Northbound traffic will be detoured to E. 105th St. East Blvd., will be closed to through traffic. E. Blvd. will be detoured using Wade Oval Dr., E. 108th St. and Wade Park Ave. Mt. Sinai Dr. will be closed to through traffic.
  • Mt. Sinai Dr. will be detoured using Chester Ave., E. 101st, Ansel Rd., Wade Park Ave. and E. 105th St. Message boards will be in place.