Chagrin River Road Bridge - Village of Moreland Hills

  • Notice to Proceed: 5/26/2020
  • Start Date: 5/26/2020
  • Completion Date: 9/1/2020
  • Project Amount: $584,795.20
  • This Page Last Updated On: 9/9/2020

Contractor:
Schirmer Construction
440-716-4900

County Project Contacts:
Darwin Merdes 216-701-1160
Mark Rinderman 440-221-2791

Approved Contract Increases:
$0

Approved Contract Decreases:
$0


PROGRESS:

September 9, 2020

  • All superstructure concrete is complete.
  • Approach slabs complete.
  • Asphalt pavement placement complete.
  • Seeding mulching of shoulders, disturbed areas adjacent to bridge nearly complete.
  • Guardrail install complete.

    One Month look ahead:
  • Completion of landscaping.
  • Completion of berm work between roadway and new guardrails.
  • Staining, sealing of parapet walls (aesthetic treatment).
  • Permanent pavement markings.
  • New signage, object markers on bridge.
  • Wiley Creek signage.

    Maintenance of Traffic:
  • Chagrin River Road on each side of Bridge 03.00 is closed to ALL traffic just south of Jackson Road. This includes bicycle and pedestrian traffic. Detour route is in place.

    Notes:
  • Project is nearly complete, opening of bridge to traveling public slated for mid-September.
  • Project now includes added work of sign and guardrail update.


August 7, 2020
  • New box beams now in place.
  • Abutments have been waterproofed, sealed, and backfilled.
  • Proposed approach slab subgrade, subbase established, areas formed up for rebar, concrete placement.
  • New concrete deck has been placed.

    One Month look ahead:
  • Place new concrete approach slabs.
  • Patch, epoxy injection repairs of existing wingwalls.
  • Rehab existing wingwalls, seal concrete surfaces.
  • New parapet placement at wingwalls and through bridge structure, stain, and seal parapets.
  • New pavement at each end of “bridge approach”.

    Maintenance of Traffic:
  • Chagrin River Road on each side of Bridge 03.00 is closed to ALL traffic just south of Jackson Road. This includes bicycle and pedestrian traffic. Detour route is in place.


June 3, 2020
  • Detour route activated.
  • Closed bridge to thru traffic on May 26, 2020.
  • Existing box beam deck structure, along with parapets, and guardrail have been removed.

    One Month look ahead:
  • Remove portions of existing abutments,
  • Patch repair existing abutments, wing walls.
  • Approach slab removal.

    Maintenance of Traffic:
  • Chagrin River Road on each side of Bridge 03.00 is closed to ALL traffic just south of Jackson Rd. This includes bicycle and pedestrian traffic. Detour route is in place.