Cedar Rd. Villages of Gates Mills & Hunting Valley

  • Notice to Proceed: 6/3/2019
  • Start Date: 6/3/2019
  • Completion Date: 9/30/2019
  • Project Amount: $1,782,778.80
  • This Page Last Updated On: 1/13/2020
Contractor:                                                              County Project Contacts:
Karvo Companies                                                      Darwin Merdes (216) 701-1160
(330) 929-9616                                                          Mark Rinderman (216) 701-4048 

Notice to Proceed:      June 2019                                    Contract Award Amount:   $1,782,778.80

Start Date:     June 2019                                                 Approved Contract Increases:  $0 
 

Scheduled Completion Date:   September 2019            Approved Contract Decreases:  $0 

Anticipated Completion Date:  September 2019       

Estimated Cost to Completion:  $1,782,778.80

PROGRESS:

Completion Date: November 2019

  • Grading of shoulders, ditch cleanout work completed.
  • Temporary pavement markings have been placed.
  • Wooden rail on barrier wall before ramps (hunting Valley) completed.
  • Proposed seeding mulching areas stabilized per winter seeding BMP.
  • New guardrail placed.

Work Expected in Spring:

  • Permanent pavement markings.
  • Seeding and mulching scheduled for April/May.

Notes:

  • A partial final was completed with Gates Mills, Hunting Valley on November 18, 2019.
  • Various work related to punch list may take place during winter months, weather permitting.

Maintenance of Traffic:

  • Cedar Road is now open to through traffic.
  • Motorists using south ramp at WYE near Chagrin River Road use caution, ramp has been configured.
  • Advance warning signs in place as needed.

November 6, 2019

  • Asphalt surface course has been completed, including intersections and drive aprons.
  • Barrier wall blasting to remove old coatings, and re-painting complete.
  • Drainage complete.
  • Shoulder grading, ditch clean out work nearly complete.

Work Expected in the upcoming weeks will include:

  • Completion of grading/ditching.
  • Construction of berms.
  • Seeding/ mulching items scheduled to be completed.
  • Wooden rails scheduled to be installed on barrier wall.
  • Permanent pavement markings scheduled for spring 2020.

Notes:

  • As of NOVEMBER 1, 2019, Cedar Road is now open to through traffic.
  • Motorist use caution when
  • using south ramp at wye near chagrin river road, ramp has been reconfigured.
  • during work hours, expect minor delays as work on shoulders in progress.

Maintenance of Traffic:

  • Advance warning signs in place as needed.
  • Flaggers on site during work operations.

August 6, 2019

  • Widening on left side from SOM Center Road to Woodstock Road complete.
  • Milling of asphalt roadway from SOM Center Road to River Road is complete.

Work Expected in the upcoming weeks will include:

  • Pavement repairs to existing road structure from SOM Center Road to River road are currently underway.
  • Intermediate course placement from SOM Center Road to Woodstock Road tentatively scheduled for the week of August 5th, date may change based of quantity of pavement repairs needed.
  • Reconstruction of south ramp to Cedar Road at River Road scheduled to begin in mid-August, along with placement of new curbing from Woodstock to 89+40 left/right.
  • Start of various drainage work scheduled for week of August 5th.

July 10, 2019

  • Widening on left side from SOM Center Road to Woodstock Road complete.

Work Expected in the upcoming weeks will include:

  • Widening on right side, SOM Center Road to Woodstock Road.
  • Milling of existing asphalt. 
  • Pavement repairs.
Notes:
  • During work hours, expect delays. Roadway is very narrow while work operations are underway
  • ALL TRAFFIC MUST SLOW DOWN, POLICE ARE ON SITE TO MONITORE DAILY
Maintenance of Traffic:
  • Cedar Road from SOM Center Road to River Road is closed, LOCAL TRAFFIC ONLY