Cedar Road Bridge #229 Rehabilitation - City of Cleveland

  • Notice to Proceed: 11/1/2016
  • Start Date: 11/1/2016
  • Completion Date: 9/1/2017
  • Project Amount: $1,953.750.00
  • This Page Last Updated On: 3/2/2017

DATE: March 2, 2017

Contractor:  
Schirmer Construction, LLC         
440-716-4900  

County Project Contacts:  

Joe Charif: (216) 348-3839

Patrick Lynch: (216) 310-8467

Notice to Proceed:  
November, 2016

Contract Award Amount: 
$1,953.750.00  

Start Date: 
November, 2016

Approved Contract Increases: $0

Scheduled Completion Date: 
September,  2017  

Approved Contract Decreases:  $0 
  

Anticipated Completion Date:  
September,  2017 

Estimated Cost to Completion: 
$1,500,000.00 

PROGRESS:

March 2, 2017

Description:

 

Rehabilitation of Cedar Road Bridge #229 over Doan Brook. Two-span reinforced concrete slab, bridge located west of the RTA/Norfolk Southern Railroad overpass on Cedar Road.

Progress:

  • Contractor currently working on east tunnel, installing reinforcing steel and formwork for proposed knee wall for aluminum culvert.