Broadrock Court Sanitary Drill Drop - City of Parma

  • Notice to Proceed: 6/1/2018
  • Start Date: 6/13/2018
  • Completion Date: 4/1/2019
  • Project Amount: $1,915,278.25
  • This Page Last Updated On: 11/9/2018

 
Contractor:  
Neron & Sons (216) 246-7705

County Project Contacts: 
Darwin Merdes (216) 701-1160
Mark Rinderman (216) 701-4048

Approved Contract Increases:  $0

Approved Contract Decreases:  $0

Anticipated Completion Date: Spring 2019 

Estimated Cost to Completion: $1,915,278.25


PROGRESS

November 9, 2018
  • DRS Enterprises has bored pilot hole for 10inch sanitary sewer from Broadrock Court To West 9th Street.  
  • Pilot hole is now being enlarges per boring methods for proposed placement of 10 Inch sanitary sewer scheduled for next week. 
One Month Look Ahead: 
  • Pulling into place, the proposed 10-inch sanitary line from Broadrock to the 5+30 drilled Shaft on Old Rockside Road.  
  • Work to start on connection out of 5+30 drilled shaft per request of Parma.  
  • Placement of manholes at Broadrock Court, 5+30 shaft on old Rockside Road. 

October 5, 2018
  • Bottom third of drilled shaft at 5 +30 on Old Rockside Road has been backfilled with grout, drop pipe in same section installed, connected to interceptor. 
  • DRS Enterprises on site to perform install of proposed 10-inch sanitary sewer by boring method. 
One Month Look Ahead:
  • Placement of proposed 10-inch sanitary line from Broadrock Court to the 5+30 drilled shaft on Old Rockside Road.
  • Work to start on connection out of 5+30 drilled shaft per request of City of Parma. 
Notes:
  • W. 9th Street to be closed to thru traffic at some point towards mid to late October for install of 10-inch sanitary sewer.  
  • W. 9th Street residents will be able to access their drives. This closure is necessary for pipe laydown area. 
Maintenance of Traffic:
  • Detour for W. 9th Street closure to use Rockside Road, to Broadview Road to Englewood.

September 6, 2018
  • Drill drop at 5 + 30, Adjacent to Old Rockside Road has been drilled. 
  • Casings placed and drop pipe connected to NEORS interceptor sewer.

One Month Look Ahead:
  • Place sub for purposed sanitary connection per request by City of Parma. 
  • Bore for replacement of new 10-inch sanitary sewer line from Broadrock Court to drill drop location.