Broadrock Court Sanitary Drill Drop - Olmsted Township

  • Notice to Proceed: 6/1/2018
  • Start Date: 6/13/2018
  • Completion Date: 10/1/2018
  • Project Amount: $1,915,278.25
  • This Page Last Updated On: 9/7/2018

 
Contractor:  
Neron & Sons (216) 246-7705

County Project Contacts: 
Darwin Merdes (216) 701-1160
Mark Rinderman (216) 701-4048

Approved Contract Increases:  $0

Approved Contract Decreases:  $0

Anticipated Completion Date: Fall 2018

Estimated Cost to Completion: $1,915,278.25


Progress

September 6, 2018
  • Drill drop at 5 + 30, Adjacent to Old Rockside Road has been drilled. 
  • Casings placed and drop pipe connected to NEORS interceptor sewer.

One Month Look Ahead:
  • Place sub for purposed sanitary connection per request by City of Parma. 
  • Bore for replacement of new 10-inch sanitary sewer line from Broadrock Court to drill drop location.