You are here: Home > Projects & Programs > Construction Updates 

Broadrock Court Sanitary Drill Drop - City of Parma

  • Notice to Proceed: 6/1/2018
  • Start Date: 6/13/2018
  • Completion Date: 4/1/2019
  • Project Amount: $1,915,278.25
  • This Page Last Updated On: 2/14/2019

 
Contractor:  
Neron & Sons (216) 246-7705

County Project Contacts: Darwin Merdes (216) 701-1160
Mark Rinderman (216) 701-4048

 

Approved Contract Increases:  
$3,654.49 (De-energize CEI)
$88,634.70 (8" Sewer Stub per Parma) 

Approved Contract Decreases:  $0

Anticipated Completion Date: Spring 2019 


PROGRESS

February 14, 2019
  • All work related to install of project bid items is complete. 
  • With exception of one area at Broadrock Court, all restoration work complete as it relates to damaged pavement and walks. 
Notes:
  • One area of pavement walk restoration remains on Broadrock Court. Completion is weather dependent, perhaps spring 2019. 
  • Tree lawn areas on West 9th Street, Old Rockside Road and Broadcrock Court have been graded and seeded. Final seeding to be completed in the spring. 
  • Final post videos of sewers to be performed as flow permits. 
Maintenance of Traffic:
  • Traffic will not be affected by remainder of work on this project. 

January 4, 2019
  • City of Parma 8-inch sanitary line from 5+30 drop shaft installed. 
  • Manhole at 14+50 Broadrock Court installed. 
One Month Look Ahead:
  • Completion of all items related to 5+30 drop shaft sewers, including backfill placement.
  • Restoration work to repair pavements at Broadrock Court, West 9th Street, weather dependent.
Notes:
  • Pavement areas at Broadrock Court and West 9th Street to be repaired this year depending on weather conditions. If weather does not permit work will be completed in the spring. 
  • Tree lawn areas have been graded and seeded. Final seeding to be completed in the spring.
Maintenance of Traffic:
  • Traffic will not be affected by remainder of work on this project.
November 9, 2018
  • DRS Enterprises has bored pilot hole for 10inch sanitary sewer from Broadrock Court To West 9th Street.  
  • Pilot hole is now being enlarges per boring methods for proposed placement of 10 Inch sanitary sewer scheduled for next week. 
One Month Look Ahead: 
  • Pulling into place, the proposed 10-inch sanitary line from Broadrock to the 5+30 drilled Shaft on Old Rockside Road.  
  • Work to start on connection out of 5+30 drilled shaft per request of Parma.  
  • Placement of manholes at Broadrock Court, 5+30 shaft on old Rockside Road. 

October 5, 2018
  • Bottom third of drilled shaft at 5 +30 on Old Rockside Road has been backfilled with grout, drop pipe in same section installed, connected to interceptor. 
  • DRS Enterprises on site to perform install of proposed 10-inch sanitary sewer by boring method. 
One Month Look Ahead:
  • Placement of proposed 10-inch sanitary line from Broadrock Court to the 5+30 drilled shaft on Old Rockside Road.
  • Work to start on connection out of 5+30 drilled shaft per request of City of Parma. 
Notes:
  • W. 9th Street to be closed to thru traffic at some point towards mid to late October for install of 10-inch sanitary sewer.  
  • W. 9th Street residents will be able to access their drives. This closure is necessary for pipe laydown area. 
Maintenance of Traffic:
  • Detour for W. 9th Street closure to use Rockside Road, to Broadview Road to Englewood.

September 6, 2018
  • Drill drop at 5 + 30, Adjacent to Old Rockside Road has been drilled. 
  • Casings placed and drop pipe connected to NEORS interceptor sewer.

One Month Look Ahead:
  • Place sub for purposed sanitary connection per request by City of Parma. 
  • Bore for replacement of new 10-inch sanitary sewer line from Broadrock Court to drill drop location.

PROGRESS:

* DRS Enterprises has completed install of 10-inch sanitary sewer from Broadrock Court to 5+30 drop shaft on Old Rockside Road.

* Nerone and Sons has installed portion of pre-cast manhole, backfill same in 5+30 drop shaft. Currently working on placement of 8-inch sanitary stub out per request from Panama City.

One Month Look Ahead:

* Completion of placement of pre-cast manholes at Broadrock Court, and at 5+30 drop shaft.

* Completion of new 8-inch sanitary line 35 feet out of 5+30 drop shaft.

* Restoration work to repair pavements at Broadrock Court, West 9th Street weather permitting.

Notes:

* West 9th Street is now open to thru traffic from Rockside Road to East Englewood. No additional closures expected.

* Pavement areas at Broadrock Court and West 9th Street to be repaired this year depending on weather conditions. If weather does not permit work will be completed in the spring.

* Tree lawn areas have been graded and seeded. Final seeding to be completed in the spring.

Maintenance of Traffic:

* Traffic will not be affected by remainder of work on this project.