- Notice to Proceed: 6/1/2020
- Start Date: 6/1/2020
- Completion Date: 12/31/2020
- Project Amount: $3,028,622.80
- This Page Last Updated On: 12/8/2020
Contractor:
Perk Company, Inc..
216-741-3933
County Project Contacts:
Ramzi Halasah 216-701-1156
Ryan Maver 216-348-3819
Approved Contract Increases: $0
Approved Contract Decreases: $0
Anticipated Completion Date: December 2020
Estimated Cost to Completion: $3,028,622.80
PROGRESS
December 8, 2020
- Brainard Road is completely open to the traveling public in all directions.
- Contractor will continue working on punch list items in the spring.
November 9, 2020
- Brainard Road is completely open to the traveling public in all directions..
- Contractor will continue working on punch list items as time/weather permits.
October 10, 2020
- Brainard Road is completely open to the traveling public in all directions.
- Contractor will continue working on punch list items as time/weather permits.
July 10, 2020
- Phase I is complete from Wilson Mills Road to Ridgebury Road.
- Phase II has begun from Ridgebury Road to Mayfield Road.
- Traffic is being maintained in one north bound lane with a detour in place.