You are here: Home > Projects & Programs > Construction Updates 

Bradford Road Pump Station Elimination in the City of Brecksville

  • Notice to Proceed: 10/1/2018
  • Start Date: 12/1/2018
  • Completion Date: 10/1/2019
  • Project Amount: $2,812,624.93
  • This Page Last Updated On: 8/6/2019

Contractor:
Terrace Construction (216) 739-3170

County Project Contacts: 
Terry Can (216) 633-0567
Ryan Maver (216) 556-3932

Notice to Proceed: October 2018
Contract Award Amount:  $2,812,624.93

Start Date:  December 2018  

Scheduled Completion Date:
October 2019 

Approved Contract Increases:  $0

Approved Contract Decreases:  $ 0

Anticipated Completion Date: July 2019



PROGRESS:

August 6, 2019

  • Restoration of Settlers Passage with new walk, drive aprons and landscaping has been completed.
  • Placement of new storm and sanitary conduit on Crinkleroot Crossing has been completed.

Upcoming Work:

  • The restoration of Crinkleroot Crossing with new roadway, drive aprons and walk has begun with roadway removal on the east side of Crinkleroot Crossing.
  • Restoration on Crinkleroot Crossing will continue through August, the pump station will be demolished, and the new sanitary line will be operational.

July 10, 2019

  • Restoration of Settlers Passage with new walk, drive aprons and landscaping has been completed.
  • Placement of new storm and sanitary conduit on Crinkleroot Crossing has been completed

    Upcoming Work:
  • Placement of sanitary conduit in the easement area at the end of Crinkleroot Crossings.
  • Demolition of the existing pump station and the restoration of Crinkleroot Crossing with a new roadway, drive aprons and walk.

May 8, 2019

  • Restoration of Settlers Passage with new walk, drive aprons and landscaping has been completed.
  • Placement of new storm and sanitary conduit on Crinkleroot Crossing has been completed.
  • Lateral tie ins to residences has been completed.

Upcoming Work:

  • Directional boring and pipe placement from the soon to be razed pump station on Hollis Lane down the slope for tie in to the new sanitary line.
  • New access road will be placed at the end of Crinkleroot Crossing.

April 10, 2019

  • Contractor is currently placing new 54” storm sewer, new manholes, as well as new drainage connections on Crinkleroot Clearing.
  • Work in April will include the restoration of drive aprons, walks and lawns on Settlers Passage.
  • The boring of sanitary conduit up the hill to Bradford Road pump station will commence.

March 11, 2019

  • New sanitary sewer line and storm sewer line installation continues.
  • Contractor has completed this work on Settler’s Passage and is now working on Crinkleroot Lane.
  • Headwall has been placed for the culvert, 72” reinforced pipe placement continues.  
February 6, 2019
  • New sanitary sewer line and storm sewer line installation continues.
  • Contractor has completed this work on Settler’s Passage and is now working on Crinkleroot Lane.

January 4, 2019

  • Work began in December at the Wiese Road and Settlers Passage intersection. 
  • Currently working on Settlers Passage, the cable tv lines are being located and moved. 
  • The sanitary/storm sewer trench is being excavated.