Bradford Road Pump Station Elimination in the City of Brecksville

  • Notice to Proceed: 10/1/2018
  • Start Date: 12/1/2018
  • Completion Date: 10/1/2019
  • Project Amount: $2,812,624.93
  • This Page Last Updated On: 2/6/2019

Contractor:
Terrace Construction (216) 739-3170

County Project Contacts: 
Terry Can (216) 633-0567
Ryan Maver (216) 556-3932

Notice to Proceed: October 2018
Contract Award Amount:  $2,812,624.93

Start Date:  December 2018  

Scheduled Completion Date:
October 2019 

Approved Contract Increases:  $0

Approved Contract Decreases:  $ 0

Anticipated Completion Date: July 2019


PROGRESS:

February 6, 2019

  • New sanitary sewer line and storm sewer line installation continues.
  • Contractor has completed this work on Settler’s Passage and is now working on Crinkleroot Lane.

January 4, 2019

  • Work began in December at the Wiese Road and Settlers Passage intersection. 
  • Currently working on Settlers Passage, the cable tv lines are being located and moved. 
  • The sanitary/storm sewer trench is being excavated.