Barton Rd., Bronson Rd. & Cook Rd - Olmsted Township/City of North Olmsted

  • Notice to Proceed: 11/1/2015
  • Start Date: 11/1/2015
  • Completion Date: 1/1/2017
  • Project Amount: $4,408,034.60
  • This Page Last Updated On: 2/23/2017
Contractor: 
Digioia Suburban Excavating (440)237-1978 

County Project Contacts:  
Mike Tworzydlo  216- 348-3895  
Todd Zima  216- 701-2359    

Notice to Proceed: November 2015  

Contract Award Amount:
$4,408,034.60

Start Date: 
November 2015   

Approved Contract Increases: 
$0

Scheduled Completion Date: 
January 2017  

Approved Contract Decreases: 
$0  

Anticipated Completion Date:  
January 2017 

Estimated Cost to Completion:
$4,408,034.60  

PROGRESS:

February 23, 2017

  • Project is complete with the exception of completing the landscaping in the spring.

October 7, 2016

Barton/Cook:

  • Complete with the exception of final striping.

Bronson:

  • Grading of ditches 50% compete with landscaping started which will be completed within one week.
  • Surface asphalt course scheduled for mid-October with final striping to follow.
  • Project will be re-opened to two-way traffic after surface course.

September 12, 2016

Barton/Cook


  • Lanscaping nearing completion.l
  • Driveways complete.
  • Surface course of asphalt to be placed next week Bronson:
  • Chip seal will be done Monday, September 12, 2016 with asphalt intermediate course to follow the next day.
  • Landscaping and driveways will be done after the intermediate course.

August 17, 2016

Barton/Cook-Paving is almost complete.

  • Completing new drive apron installation. Once complete, new surface course of asphalt will be put down.

Bronson-New water taps are 50% complete. Once taps are complete, existing road to be stabilized and paved (approximately within one month).

  • Once stabilization occurs, chip seal and asphalt intermediate course will be put down.

  • New drive aprons then will be installed followed by surface course and landscaping.

  •  

June 30, 2016

  • Barton/Cook-Pavement repairs are 50% complete.
  • Sewers complete; except to put intermediate asphalt course in the next two weeks.
  • Bronson-Sewers complete.
  • Waterline is 90% complete.
  • Boring new waterline under railroad to resume July 5, 2016 (due to railroad delays).
  • Boring will be 24/7 for 2-3 days.
  • Water service connections to begin.

June 8, 2016

  • All storm, sanitary and waterlines are installed with the exception of 60’ of waterline underneath the railroad tracks on Bronson Road. This work will be completed next week.
  • Paving on Cook Road and Barton Road should begin in the next couple of weeks. Contractor will linear grading, landscaping and pavement markings.

June 8, 2016

  • All storm, sanitary and waterlines are installed with the exception of 60’ of waterline underneath the railroad tracks on Bronson Road. This work will be completed next week.
  • Paving on Cook Road and Barton Road should begin in the next couple of weeks. Contractor will linear grading, landscaping and pavement markings.

April 8, 2016

  • Barton sewers complete.
  • When the other two streets have sewers completed, Barton Rd. will then be paved. 
  • Cook sanitary sewers are complete.
  • Some storm sewer work will begin next week.
  • Paving will begin when Bronson Rd. is complete.
  • Bronson sanitary sewer main is 50% complete.
  • Once the main is complete, work on the laterals will begin.