Barrett Road Resurfacing Independence

  • Notice to Proceed: 7/30/2018
  • Start Date: 8/15/2018
  • Completion Date: 9/4/2018
  • Project Amount: $389,242.20
  • This Page Last Updated On: 11/9/2018

 

Contractor:  Cook Paving Company   (216) 2467-7705  

County Project Contacts: Darwin Merdes (216) 701-1160 /  Mark Rinderman (216) 701-4048

Notice to Proceed: July 30, 2018                                     Contract Award Amount:  $389,242.20

Start Date: August 15, 2018                                            Approved Contract Increases:  $0

Scheduled Completion Date: September 28, 2018         Approved Contract Decreases:  $0

Anticipated Completion Date: September 2018            

Estimated Cost to Completion:  $389,242.20

PROGRESS:

November 9, 2018
  • Project is complete as of October 1, 2018, with the installation of items related to seeding/mulching.  
  • Previous to this week, paving was completed on 9/12, with berm install, ditch work, and pavement markings completed last week. 
One Month Look Ahead:
  • Final inspection to be scheduled this month, November. 
Maintenance of Traffic
  • Roadway upgrade has been completed, open to normal traffic pattern. 

October 5, 2018
  • Project is complete as of October 1, 2018, with the installation of items related to seeding/mulching. 
  • Before this week, paving was completed on 9/12, with berm install, ditch work, And pavement markings completed last week. 
One Month Look Ahead:
  • Final inspection this month. 
Maintenance of Traffic
  • Roadway upgrade has been completed, open to normal traffic pattern.

September 6, 2018
  • Roadway has been planned from Lewis Road to Spafford Road.
  • Full depth pavement repairs, including asphalt shoulder repair has been completed.
  • Slope stabilization of Spafford Road between Barrett Road and Valley View was completed on 8/31.
  • Spafford Road is open to normal traffic pattern.

One Month Look Ahead:

  • Chip seal to be placed the week of 9/3.
  • Paving of intermediate and wearing course to follow.
  • Various shoulder work to be completed within the next two weeks, including ditch cleanout work.
  • Permanent striping and landscaping work will be completed at the end of project.

Notes:

  • Based on work completed, project completion is slated for late September, Early October.

Maintenance of Traffic

  • Roadway to stay open at all times.
  • One lane of traffic will be maintained each way during work hours with the use of flaggers.
  • EXPECT DELAYS