Barrett Road Improvement from Berea Corporation Line to Lewis Road In Olmsted Township

  • Notice to Proceed: 9/10/2012
  • Start Date: 11/6/2012
  • Completion Date: 10/1/2013
  • Project Amount: $2,321,156.59
  • This Page Last Updated On: 4/2/2013
Contractor: Digioia Suburban Excavating (440) 564-1011
County Project Contacts: Darwin Merdes (216) 348-4073 / Pat Kearney (216) 260-6075


Progress


April 2, 2013
  • DiGioia Suburban has completed the excavation for and placement of all the new service connections to the right-of-way throughout the project.
  • Work for continues for drainage, embankment and excavation items.
  • Barrett Road between Olmsted Township/Berea Corporation Line and Spafford Road is closed to thru traffic.
  • Local access will be maintained.


March 6, 2013
  • DiGioia Suburban is continuing with the work involved for proposed culvert #11.
  • Work for new storm sewers, catch basins and manholes throughout the project is in progress.
  • Weather permitting the contractor will begin with the excavation for and placement of the water service connections within the next few weeks.
  • Barrett Road between Olmsted Township/Berea Corporation Line and Spafford Road is closed to thru traffic.
  • Local access will be maintained.


February 2, 2013
  • DiGioia Suburban has begun the work for proposed culvert #8.
  • Work for new storm sewers, catch basins and manholes throughout the project is in progress.
  • Weather permitting the contractor will begin with the excavation for and placement of the water service connections within the next few weeks.
  • Barrett Road between Olmsted Township/Berea Corporation Line and Spafford Road is closed to thru traffic.
  • Local access will be maintained.


January 2, 2013
  • DiGioia Suburban has begun the work for proposed culvert #8.
  • The excavation for and placement of the new 12” water main and fire hydrants has been completed.
  • The contractor will begin the excavation for and placement of the new water service connections with in the next couple of weeks.
  • Barrett Road between Olmsted Township/Berea corporation line and Spafford Road is closed to thru traffic. Local access will be maintained.


December 2012
  • The excavation for and placement of the new 12’ water main should be completed by 12‐10‐12.
  • After the completion of the new main the contractor will begin the excavation for and placement of the new water service connections.
  • Barrett Road is closed to thru traffic. Local access will be maintained.


October 2012
  • Surveyors are on the project site performing lay‐out work for the project construction limits.
  • Excavation for and placement of the new main is scheduled to begin on November 6, 2012.