- Notice to Proceed: 9/10/2012
- Start Date: 11/6/2012
- Completion Date: 10/1/2013
- Project Amount: $2,321,156.59
- This Page Last Updated On: 4/2/2013
Contractor: Digioia Suburban Excavating (440) 564-1011
County Project Contacts: Darwin Merdes (216) 348-4073 / Pat Kearney (216) 260-6075
Progress
April 2, 2013
- DiGioia Suburban has completed the excavation for and placement of all the new service connections to the right-of-way throughout the project.
- Work for continues for drainage, embankment and excavation items.
- Barrett Road between Olmsted Township/Berea Corporation Line and Spafford Road is closed to thru traffic.
- Local access will be maintained.
March 6, 2013
- DiGioia Suburban is continuing with the work involved for proposed culvert #11.
- Work for new storm sewers, catch basins and manholes throughout the project is in progress.
- Weather permitting the contractor will begin with the excavation for and placement of the water service connections within the next few weeks.
- Barrett Road between Olmsted Township/Berea Corporation Line and Spafford Road is closed to thru traffic.
- Local access will be maintained.
February 2, 2013
- DiGioia Suburban has begun the work for proposed culvert #8.
- Work for new storm sewers, catch basins and manholes throughout the project is in progress.
- Weather permitting the contractor will begin with the excavation for and placement of the water service connections within the next few weeks.
- Barrett Road between Olmsted Township/Berea Corporation Line and Spafford Road is closed to thru traffic.
- Local access will be maintained.
January 2, 2013
- DiGioia Suburban has begun the work for proposed culvert #8.
- The excavation for and placement of the new 12” water main and fire hydrants has been completed.
- The contractor will begin the excavation for and placement of the new water service connections with in the next couple of weeks.
- Barrett Road between Olmsted Township/Berea corporation line and Spafford Road is closed to thru traffic. Local access will be maintained.
December 2012
- The excavation for and placement of the new 12’ water main should be completed by 12‐10‐12.
- After the completion of the new main the contractor will begin the excavation for and placement of the new water service connections.
- Barrett Road is closed to thru traffic. Local access will be maintained.
October 2012
- Surveyors are on the project site performing lay‐out work for the project construction limits.
- Excavation for and placement of the new main is scheduled to begin on November 6, 2012.