You are here: Home > Projects & Programs > Construction Updates 

Bagley Rd. / Olmsted Township Resurfacing

  • Notice to Proceed: 2/1/2017
  • Start Date: 2/1/2017
  • Completion Date: 2/1/2018
  • Project Amount: $6,973,651.30
  • This Page Last Updated On: 11/6/2017

 
Date:  
March 2, 2017

Contractor:  Fabrizi Recycling  440-234-1284

County Project Contacts:

Joe Charif:
(216) 701-1262 

Terry Cain: (216) 857-4056

Notice to Proceed: February 2017 

Start Date: 
February 2017

Scheduled Completion Date: February 2018

Contract Award Amount: $6,973,651.30

Approved Contract Increases: 
 $0

Approved Contract Decreases:  $0

Anticipated Completion Date: February 2018

Estimated Cost to Completion:  $6,973,651.30


PROGRESS:

November 2, 2017
  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • The installation of the new sanitary line has been completed.
  • Placement of new sidewalk, drive aprons, asphalt pavement and landscaping has been completed between Old Fitch Road and Stearns Road.
  • In the next thirty days placement of surface course asphalt will be completed, roadsides will be bermed, new drive aprons will be placed and the project will be landscaped. Castings will be set to grade; new drive aprons will be placed and the sanitary force main will be placed.

October 10, 2017

  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • The installation of the new sanitary line has been completed.
  • Placement of new sidewalk, drive aprons, asphalt pavement and landscaping has been completed between Old Fitch Road and Stearns Road.
  • Currently existing asphalt pavement is being milled from Stearns Road to the Lorain County Line, base asphalt is being placed in the milled areas.
  • Following placement of the base asphalt, intermediate asphalt will be placed.
  • In the next thirty days castings will be set to grade, new drive aprons will be placed and the sanitary force main will be placed.


September 1, 2017


  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • The installation of the new sanitary line has been completed.
  • Placement of new sidewalk, drive aprons, asphalt pavement and landscaping has been completed between Old Fitch Road and Stearns Road
  • Work this month will include milling of the existing pavement, placement of the sanitary force main and completion of the sanitary pump station west of Stearns Road, to the Lorain County line


August 3, 2017

  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • New sidewalk and driveway aprons have been placed east of Stearns Road.
  • Currently sanitary laterals are being installed and will be completed in August.
  • Bagley Road, east of Stearns Road is in the process of existing asphalt removal, followed by base repair. Then the base will be chip sealed and intermediate course asphalt will be placed prior to school opening in late August.
  • New sidewalk will continue to be placed east of Stearns Road.



July 7, 2017

  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • Currently the contractor is tapping into the new water main and placing sanitary line laterals.
  • Drainage work has begun east of Stearns Road.

June 6, 2017

 

 

  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • Currently the contractor will continue the installation of the new sanitary line and start tapping into the new water main.

 

 



May 3, 2017  

  • The new 12” water main between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County line has been completed.
  • Currently and throughout May the contractor will continue the installation of the new sanitary line.  

     




    March 2, 2017
  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • Currently, the contractor is installing the new 12" water main between Stearns Road and Bronson Road.
  • Work in March will include completion of the water main and installation of the new 8" sanitary force main.