Bagley Rd. / Olmsted Township Resurfacing

  • Notice to Proceed: 2/1/2017
  • Start Date: 2/1/2017
  • Completion Date: 2/1/2018
  • Project Amount: $6,973,651.30
  • This Page Last Updated On: 6/7/2017

 


Date:  
March 2, 2017

Contractor:  Fabrizi Recycling  440-234-1284

County Project Contacts:

Joe Charif:
(216) 701-1262 

Terry Cain: (216) 857-4056

Notice to Proceed: February 2017 

Start Date: 
February 2017

Scheduled Completion Date: February 2018

Contract Award Amount: $6,973,651.30

Approved Contract Increases: 
 $0

Approved Contract Decreases:  $0

Anticipated Completion Date: February 2018

Estimated Cost to Completion: 
 $6,973,651.30



PROGRESS:

June 6, 2017


  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main line between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County Line have been completed.
  • Currently the contractor will continue the installation of the new sanitary line and start tapping into the new water main.
May 3, 2017

  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • The new 12” water main between Stearns Road and Bronson Road, as well as the new 8” water main between Bronson Road and the Lorain County line has been completed.
  • Currently and throughout May the contractor will continue the installation of the new sanitary line.

March 2, 2017

  • Traffic on Bagley Road from Stearns Road to the Lorain County Line is being maintained westbound only for local residents.
  • Currently, the contractor is installing the new 12" water main between Stearns Road and Bronson Road.
  • Work in March will include completion of the water main and installation of the new 8" sanitary force main.