Bagley Road - Olmsted Township

  • Notice to Proceed: 7/1/2015
  • Start Date: 7/1/2015
  • Completion Date: 11/30/2018
  • Project Amount: $1,251,754.00
  • This Page Last Updated On: 10/10/2018

Date:  September 10, 2018

Contractor:  Kokosing Construction / 440-322-2665

County Project Contacts: 
 Terry Cain (216) 633-0567 
 Ryan Maver (440) 759-2472

Notice to Proceed: July 2018

Contract Award Amount:  $1,251,754.00

Start Date:  August 2018
Approved Contract Increases:   $0

Scheduled Completion Date:  November 2018
Approved Contract Decreases:  $0

Anticipated Completion Date:  November 2018
Estimated Cost to Completion:  $1,251,754.00

PROGRESS:

October 10, 2018

  • 13/4 inches of leveling course asphalt has been placed.
  • Castings in the roadway are being adjusted to grade.
  • New drive aprons are being placed where necessary.
  • New walk and curb ramps are being placed.

 September 10, 2018

  • Currently the contractor is milling the top 3 inches of asphalt from the roadway.
  • The remainder of the month will see the milled surface be repaired as needed, 1 and 3/4 inches of leveling course asphalt will then be placed.
  • Castings in the roadway will then be adjusted to grade.