Bagley Road Bridge- #0345 Replacement Olmsted Falls

  • Notice to Proceed: 7/1/2016
  • Start Date: 6/1/2017
  • Completion Date: 10/13/2017
  • Project Amount: $2,287,223.15
  • This Page Last Updated On: 3/2/2017

DATE: July 2016

Contractor:  
Schirmer Construction, LLC         
440-716-4900  

County Project Contacts:  

Joe Charif: (216) 348-3839

   
Notice to Proceed:  
July 2016  

Contract Award Amount: 
$22,945,485.17   

Start Date: 
July 2016

Approved Contract Increases: $0

Scheduled Completion Date: 
June, 2017  

Approved Contract Decreases:  $0 
  

Anticipated Completion Date:  
October 13, 2017

Estimated Cost to Completion: 
$2,287,223.15 

PROGRESS:

March 2, 2017

  • Detour route has been in effect since November 1, 2016.
  • Existing sidewalk was removed and replaced as needed on Brookside Road for the pedestrian detour.
  • Existing asphalt milled from on Mapleway Drive and Bagley Road, new asphalt placed for motorist detour.
  • A right turn lane was placed on Mill Street at Columbia Road to alleviate traffic congestion.
  • Police Officers with patrol cars direct traffic during the morning and evening rush hours.
  • The existing bridge has been demolished and removed and contractor has placed drilled shafts.
  • Currently front and rear footers as well as the abutments are being built.
  • Structures will then be waterproofed.
  • Porous backfill will be placed.
  • Gabion walls will be built.
February 23, 2017
  • Detour route has been in effect since November 1, 2016.
  • Existing sidewalk was removed and replaced as needed on Brookside Road for the pedestrian detour.
  • Existing asphalt milled from on Mapleway Drive and Bagley Road, new asphalt placed for motorist detour.
  • A right turn lane was placed on Mill Street at Columbia Road to alleviate traffic congestion.
  • Police Officers with patrol cars direct traffic during the morning and evening rush hours.
  • The existing bridge has been demolished and removed.
  • Contractor has been excavating down to and breaking rock, drilling for placement of concrete shafts and will be placing footers to locate the existing water main to accommodate the new structure.

October 7, 2016
  • Bridge work has not begun.
  • Expected bridge and road closure in November for the winter months.
  • Bridge demolished and foundation work to begin at this time.
  • Bagley Rd., and Mapleway Dr. has been recently re-paved with final pavement makings to be completed.
  • Sidewalk replacement work was completed on Broookside Rd., and Mill Street