Bagley Road Bridge- #0345 Replacement Olmsted Falls

  • Notice to Proceed: 7/1/2016
  • Start Date: 6/1/2017
  • Completion Date: 10/13/2017
  • Project Amount: $2,287,223.15
  • This Page Last Updated On: 6/7/2017
Date: July 2016

Contractor:  
Schirmer Construction, LLC     

County Project Contacts:  
Joe Charif: (216) 348-3839
Terry Cain: (216) 857-4056 
   
Notice to Proceed:  
July 2016  

Contract Award Amount: 
$22,945,485.17   

Start Date: 
July 2016

Approved Contract Increases: $0

Scheduled Completion Date: 
June, 2017  

Approved Contract Decreases:  $0 
  

Anticipated Completion Date:  
October 13, 2017

Estimated Cost to Completion: 
$2,287,223.15
 

PROGRESS: 

June 6, 2017
  • Detour route has been in effect since November 1, 2016.
  • Existing sidewalk was removed and replaced as needed on Brookside Road for the pedestrian detour.

  • Existing asphalt milled from Mapleway Drive and Bagley Road, new asphalt placed for motorist detour.

  • A right turn lane was placed on Mill Street at Columbia Road to alleviate traffic congestion.
  • The existing bridge has been demolished and removed.
  • New footers and abutments have been erected.
  • New pre-cast box beams have been placed.
  • Installation of new drainage structures has been completed on the east and west side of the bridge.  
  • New concrete bridge deck and approach slabs have been placed.
  • New parapet walls have been erected.
  • Placement of new curb and concrete roadway on the east side of the bridge and removal and replacement of asphalt roadway and curb on the west side of the bridge has been completed.
  • Bagley Road in now open to westbound traffic.
  • Work in June will include the completion of new parapet walls, placement of concrete drive aprons and landscaping.

    May 3, 2017

      • Detour route has been in effect since November 1, 2016.
      • Existing sidewalk was removed and replaced as needed on Brookside Road for the pedestrian detour.
      • Existing asphalt milled from Mapleway Drive and Bagley Road, new asphalt placed for motorist detour.
      • A right turn lane was placed on Mill Street at Columbia Road to alleviate traffic congestion.
      • Police Officers with patrol cars direct traffic during the morning and evening rush hours.
      • The existing bridge has been demolished and removed.
      • New footers and abutments have been erected.
      • New pre-cast box beams have been placed.
      • Installation of new drainage structures has been completed on the east side of the bridge and currently new drainage is being installed on the west side.
      • New concrete bridge deck and approach slabs have been placed.
      • Work in May will include the completion of new drainage on the west side of the bridge.
      • Placement of the new curb and roadway on the east side of the bridge and removal and replacement of asphalt roadway and curb on the west side of the bridge.


      March 2, 2017

      • Detour route has been in effect since November 1, 2016.
      • Existing sidewalk was removed and replaced as needed on Brookside Road for the pedestrian detour.
      • Existing asphalt milled from on Mapleway Drive and Bagley Road, new asphalt placed for motorist detour.
      • A right turn lane was placed on Mill Street at Columbia Road to alleviate traffic congestion.
      • Police Officers with patrol cars direct traffic during the morning and evening rush hours.
      • The existing bridge has been demolished and removed and contractor has placed drilled shafts.
      • Currently front and rear footers as well as the abutments are being built.
      • Structures will then be waterproofed.
      • Porous backfill will be placed.
      • Gabion walls will be built.

      February 23, 2017

      • Detour route has been in effect since November 1, 2016.
      • Existing sidewalk was removed and replaced as needed on Brookside Road for the pedestrian detour.
      • Existing asphalt milled from on Mapleway Drive and Bagley Road, new asphalt placed for motorist detour.
      • A right turn lane was placed on Mill Street at Columbia Road to alleviate traffic congestion.
      • Police Officers with patrol cars direct traffic during the morning and evening rush hours.
      • The existing bridge has been demolished and removed.
      • Contractor has been excavating down to and breaking rock, drilling for placement of concrete shafts and will be placing footers to locate the existing water main to accommodate the new structure.

      October 7, 2016
      • Bridge work has not begun.
      • Expected bridge and road closure in November for the winter months.
      • Bridge demolished and foundation work to begin at this time.
      • Bagley Rd., and Mapleway Dr. has been recently re-paved with final pavement makings to be completed.
      • Sidewalk replacement work was completed on Broookside Rd., and Mill Street