You are here: Home > Projects & Programs > Construction Updates 

Bagley Rd. /Pleasant Valley Rd. From Pearl Rd. to York Rd. Cities of Middleburg Heights & Parma

  • Notice to Proceed: 3/16/2015
  • Start Date: 3/3/2016
  • Completion Date: 10/13/2017
  • Project Amount: $22,945,485.17
  • This Page Last Updated On: 4/7/2017

DATE:
August 8, 2016

Contractor:  
Perk Company         
216-391-1444  

County Project Contacts:  
Mike Tworzydlo   216-348-3895
Patrick Kearney 440-884-3356   

Notice to Proceed:  
March 16, 2015  

Contract Award Amount: 
$22,945,485.17   

Start Date: 
March 3, 2015 

Approved Contract Increases: $0

Scheduled Completion Date: 
October 13, 2017  

Approved Contract Decreases:  $0   

Anticipated Completion Date:  
October 13, 2017

Estimated Cost to Completion: 
$22,945,485.17  

PROGRESS:

April 7, 2017
  • Section 1 (W. 130th to York Road)
  • Pavement removal south side from approximately Ann Arbor Ave. to West 130th Street.
  • Next month will progress from pavement removal to new concrete pavement installation.
  • Section 2 (W. 130th Street to Pearl Road)
  • Underground work completed.
  • Temporary pavement installed on north side.
  • Traffic moved to south side form W. 130th Street to Baldwin Reserve in order to have pavement removed.
  • After Section 1 pavement removal and installation, this section will be next.
  • General landscaping and repair will be begin soon.

February 23, 2017
  • Work has begun on the sewer laterals between W. 130th Street and Pearl Road.
  • Temporary pavement will be installed with the month.
    Maintenance of Traffic:
  • West Pleasant Valley Road between Oakwood Road and West 130th Street is closed to thru traffic until the work for the relocation of the Oakwood Road and Pleasant Valley Road intersection has been complete.
November 10, 2016:

  • The new concrete roadway on the north side of Pleasant Valley Road in Parma between Greenleaf Avenue and West 130th was placed on Friday, October 28, 2016.
  • Work for the new concrete driveways and sidewalks on the north side of Pleasant Valley Road in Parma between Greenleaf Avenue and West 130th Street has begun.
  • The contractor has resumed the excavation for and placement of the new storm sewers and lateral connections on Bagley Road in Middleburg Heights between West 130th Street and Baldwin Creek Drive.
  • Work for the second phase of Bridge #116 on Bagley Road between Baldwin Creek Drive and Pearl Road is on hold until the Illuminating Company can complete their utility relocation work.
  • Work for the new sanitary sewer main on Pleasant Valley Road between West 130th Street and Parma Park has been completed.

Maintenance of Traffic:

  • West Pleasant Valley Road between Oakwood Road and West 130th Street is closed to thru traffic until the work for the relocation of the Oakwood Road and Pleasant Valley Road intersection has been complete.
  • The left turn lane heading east on Pleasant Valley Road at the entrance to Tri-C has been re-established.
  • During the placement of the new storm sewer and laterals on Bagley Road between West 130th Street and Baldwin Creek Drive, one land bi-directional traffic is being maintained with police officers.

October 7, 2016

  • The new concrete roadway on the north side of Pleasant Valley Road in section #1 between Sesquicentennial Drive and Greenleaf Avenue is scheduled to be placed on Friday, October 7, 2016 (weather permitting).
  • Work for the new concrete driveways and sidewalks on the north side of Pleasant Valley Road between Parma Park and West 130th Street will begin after the concrete for the roadway in this area has cured.
  • The new concrete roadway on the north side of Pleasant Valley Road between Greenleaf Avenue and W. 130th Street is scheduled to be placed by Friday, October 28, 2016 (weather permitting).
  • Work for the second phase of Bridge #116 on Bagley Road between Baldwin Creek Drive and Pearl Road is on hold until the Illuminating Company can complete their utility relocation work.
  • Work for the new sanitary sewer main on Pleasant Valley Road between West 130th Street and Parma Park has begun and is scheduled to be completed by October 10, 2016 (weather permitting).

Maintenance of Traffic:

  • West Pleasant Valley Road between Oakwood Road and West 130th Street closed to thru traffic until the work for the relocation of the Oakwood Road and Pleasant Valley Road intersection has been complete.
  • The left turn lane heading east on Pleasant Valley Road at the entrance to Tri-C has been re-established.
  • During the placement of the sanitary sewer work on the north side of Pleasant Valley Road between West 130th Street and Parma Park, one lane bi-directional traffic is being maintained with police officers.

August 9, 2016

  • The new concrete roadway on the north side of Pleasant Valley Road in section #1 between Ann Arbor Drive and York Road has been completed.
  • Work continues for the intersection of Ann Arbor Drive and Pleasant Valley Road as well as Malibu Drive and Pleasant Valley Road.  
  • The new concrete driveways have been placed on the north side of Pleasant Valley Road between Ann Arbor Drive and York Road.
  • Excavation for and placement of the new concrete sidewalks and curb ramps has begun in the same area.
  • Work continues for the second phase of Bridge No. #116 on Bagley Road between Baldwin Creek and Pearl Road.  
  • Storm sewer work on the north side of the roadway in section #2 between W. 130th Street and Baldwin Creek Drive is in progress.
  • Work for the new sanitary sewer main in section #1 between W. 130th Street and Parma Park is scheduled to resume August 15, 2016.  

Maintenance of Traffic:  

  • Temporary pavement has been placed on the south side of Pleasant Valley Road at Bridge #144. Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.  
  • There is no left turn heading east on Pleasant Valley Road at the entrance to Tri-C, motorists should go to York Road, turn left and use the York Road entrances to Tri-C.  
  • During the placement of the storm sewer work on the north side of the roadway in section #2 between W. 130th Street and Baldwin Creek Drive, one lane bi-directional traffic is being maintained with police officers.  
July 6, 2016

  • The new concrete roadway on the north side of Pleasant Valley Road in section #1 between Ann Arbor Drive and York Road has been completed.
  • Work has begun for the intersection of Ann Arbor and Pleasant Valley Road as well as the intersection of Malibu Drive and Pleasant Valley Road.
  • New concrete drive aprons have been placed on the north side of Pleasant Valley Road between Ann Arbor Drive and York Road.
  • Excavation for and placement of the new driveways has begun in the same area.
  • Work has begun for the second phase of Bridge #116 on Bagley Road between Baldwin Creek Drive and Pearl Road.

    Maintenance of Traffic:
    • Temporary pavement has been placed on the south side of Pleasant Valley Road at Bridge #144. Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130 th Street is being maintained.
    • Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.
    • There is no left turn heading east on Pleasant Valley Road at the entrance to Tri-C, motorists should go to York Road, turn left and use the York Road entrances to Tri-C.

    June 8, 2016

  • The first two lanes of concrete roadway on the north side of Pleasant Valley Road in section #1 between Malibu Drive and York Road has been completed and the curb lane is scheduled to be placed on June 7, 2016.
  • Work has been completed for the second phase of Bridge #44 on Pleasant Valley Road between W. 130th Street and West Pleasant Valley Road. The back-filing in this area has begun.
  • Sanitary sewer work on Pleasant Valley Road between W. 130th Street and Parma Park is scheduled to begin the week of June 6, 2016.

Maintenance of Traffic:

  • Temporary pavement has been placed on the south side of Pleasant Valley Road at Bridge #144. Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.
  • Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.
  • There is no left turn heading east on Pleasant Valley Road at the entrance to Tri-C., drivers should go to York Road, turn left and use the York Road entrances to Tri-C.

May 5, 2016

  • Storm sewer work on the north side of Pleasant Valley Road in section #1 between Ann Arbor and York Road has been completed and the removal of the existing roadway and driveway pavements in this section have begun.
  • Work continues for the second phase Bridge #144 on Pleasant Valley Road between W. 130th Street and West Pleasant Valley Road.
  • Storm water continues on Bagley Road in section #2 between W. 130th and Pearl Road.

Maintenance of Traffic:

  • The removal of the existing roadway and driveway pavement on the north side of Pleasant Valley Road beginning at York Road and heading east to Parma Park has begun.
  • Once the old pavement has been removed in front of the homes on the south side of the road residents can access their directly from the new concrete roadway on the north side.  
  • Temporary pavement has been placed on the south side of Pleasant Valley Road at Bridge #144.  
  • Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.  
  • There is no left turn heading east on Pleasant Valley Road at the entrance to Tri-C., drivers should go to York Road, turn left and use the York Road entrances to Tri-C. 

April 5, 2016

  • The second phase of work has begun for Bridge #144 on Pleasant Valley Road between W. 130th Street and West Pleasant Valley Road.
  • The second phase of work has begun for Bridge #116 on Bagley Road between Hyde Park and Baldwin Creek Drive.
  • Work has begun for the placement of concrete sidewalks and drive aprons on W. 130th Street between Bagley Road and Old Pleasant Valley Road.

Work Expected in the Next 30 Days:

  • Storm sewer work on the north side of Pleasant Valley Road in Section #1 between Ann Arbor and York Road will continue.
  • After the completion of the storm sewers on the north side of Pleasant Valley Road In section #1 between Ann Arbor and York Road the contractor will remove the Existing roadway pavement in this area and begin the set up for the proposed concrete roadway.
  • The second phase of work will continue for Bridge #144 on Pleasant Valley Road between W. 130th and West Pleasant Valley Road.
  • Storm sewer crossings on Bagley road in section #2 between W. 130th and Pearl Road will continue.
  • The second phase of work will continue for Bridge #116 on Bagley Road between Hyde Park and Baldwin Creek Drive. This will include the lowering of the existing 12 inch water main in the same area.

Maintenance of Traffic

  • On Monday, February 22, 2016 through bi-directional traffic on Pleasant Valley Road was moved to the new concrete pavement on the north side of Pleasant Valley Road between York Road and Parma Park.
  • The old/existing Pleasant Valley Road in front of the homes on the south side in this section is limited to use by residents to access their homes.
  • Temporary pavement has been placed on the south side of Pleasant Valley Road at Bridge #144.
  • Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.
  • There is no left turn heading east on Pleasant Valley Road at the entrance to Tri-C., drivers should go to York Road, turn left and use the York Road entrances to Tri-C.
  • Due to the work that is needed for the storm sewer crossings on Bagley Road in section #2 between 130th and Pearl Road there have been long delays for through traffic.
  • Through traffic between the hours of 7:00 a.m. and 6:00 p.m. should use the detour that is in place.
  • For Bagley Rd. eastbound at the Pearl Road intersection, the detour is northbound on Pearl Road to Smith Road eastbound to W. 130th Street northbound to Bagley/Pleasant Valley.
  • For westbound at Pleasant Valley and W. 130th Street intersection the detour is north to Smith Road eastbound to Pearl Road southbound to Bagley Road.

March 4, 2016

  • Storm sewer work on the north side of Pleasant Valley Road in section #1 between Ann Arbor and York Road has begun.
  • Storm sewer work continues on Bagley Road in section #2 between W. 130th Street and Pearl Road.
  • The second phase of work has begun for Bridge #144 on Pleasant Valley Road between W. 130th Street and West Pleasant Valley Road.

Maintenance of Traffice:


  • On Monday, February 22, 2016 through bi-directional traffic on Pleasant Valley Road was moved to the new concrete pavement on the north side of Pleasant Valley Road between York Road and Parma Park.
  • The old/existing pleasant Valley Road in front of the homes on the south side in this section is limited to use by residents to access their homes.
  • Temporary pavement has been placed on the south side of Pleasant Valley Road at bridge #144.
  • Normal two lane bi-directional traffic between West Pleasant Valley Road and West 130th Street is being maintained.
  • There is no left turn heading east on Pleasant Valley Road at the entrance to Tri-C., drivers should go to York Road, turn left and use the York Road entrances to Tri-C.

January 11, 2016

  • The new concrete pavement has been placed on the north side of Pleasant Valley Road between York Rd. and Parma Park.
  • Storm sewer work continues on Bagley Road in section #2 between W. 130th and Pearl Road.
  • Work will continue on north side of bridge #116 on Bagley Road between Hyde Park and Baldwin Creek after the Illuminating Company moves the utility poles from the north side of the roadway to the south side of the roadway.
  • The precast concrete arch sections for phase #1 on Bridge #144 on Pleasant Valley Road between W. 130th and West Pleasant Valley Road are scheduled to be installed on January 12, 2016.

Maintenance of Traffic:

  • Temporary pavement has been placed on the south side of Bagley Road at Bridge #116 and normal two lane bi-directional traffic between Hyde Park and Baldwin Creek is being maintained.
  • There is no left turn heading east on Pleasant Valley Road at the entrance of Tri-C, drivers should go to York Rd., turn left and use the York Rd., entrance to Tri-C.

October 2, 2015

  • The new concrete pavement has been placed on the north side of Pleasant Valley Road between York Rd. and Malibu Drive.
  • New concrete pavement on the north side of Pleasant Valley Rd. between Malibu Drive and Parma Park is scheduled to be placed on Friday, October 2, 2015.
  • Workers began the removal of the existing roadway pavement and excavation for the proposed 10’ concrete roadway pavement at the northwest quadrant of the intersection of Bagley/Pleasant Valley Road & W. 130th Street.
  • Storm sewer and sanitary sewer work continues on Pleasant Valley Road in section #1 between W. 130th and York Rd.
  • Work continues on bridge #116 on Bagley Road between Hyde Park and Baldwin Creek.
  • Work has resumed on Bridge #144 on Pleasant Valley Road between W. 130th and West Pleasant Valley Road. Maintenance of Traffic:
  • One-way bi-directional traffic on Bagley Rd. at Bridge No. 116 is maintained with temporary traffic signals between Hyde Park and Baldwin Creek.
  • There is no left turn heading east on Pleasant Valley Road at the entrance of Tri-C

September, 2015 
  • Workers began the removal of the existing roadway pavement and excavation for the proposed 10" concrete roadway pavement on the north side of Pleasant Valley from York Road to Ann Arbor.
  • Storm sewer and sanitary sewer work continues on Pleasant Valley Road in Section #1 between W. 130th and York Road.
  • Work continues on bridge #116 on Bagley Road between Hyde Park and Baldwin Creek.
  • Work on Bridge #144 on Pleasant Valley Road between W. 130th and West Pleasant Valley Road is on hold until after Labor Day.

    Maintenance of Traffic:

  • One-way bi-directional traffic on Bagley Rd. at bridge #116 is maintained with temporary traffic signals between Hyde Park and Baldwin Creek.

The entrance to Tri-C on Pleasant Valley Rd. is now open

July, 2015

  • Work continues on bridge No. 116 on Bagley Rd. between Hyde Park and Baldwin Creek.
  • Work on Bridge No. 144 on Pleasant Valley Rd. between W. 130th and W. Pleasant Valley Rd. is on hold until after Labor Day.
  • Road work continues on the entrance to Tri-C at Pleasant Valley Rd.

Maintenance of Traffic:

  • West 130th Street at Bagley Rd. is now open to through traffic.
  • One-way bi-directional traffic on Bagley Rd. at Bridge No. 116 is maintained with temporary traffic signals between Hyde Park and Baldwin Creek.
  • The entrance to Tri-C on Pleasant Valley Rd. is scheduled to re-open on Wednesday, August 5, 2015.