Bagley Rd. /Pleasant Valley Rd. From Pearl Rd. to York Rd. Cities of Middleburg Heights & Parma

  • Notice to Proceed: 3/16/2015
  • Start Date: 3/3/2015
  • Completion Date: 7/1/2018
  • Project Amount: $22,945,485.17
  • This Page Last Updated On: 11/6/2019

Contractor:  
Perk Company         
216-391-1444  

County Project Contacts:  
Mike Tworzydlo   216-348-3895

Notice to Proceed:  
March 16, 2015  

Contract Award Amount: 
$22,945,485.17   

Start Date: 
March 3, 2015 

Approved Contract Increases: $0

Scheduled Completion Date: 
July 2018  

Approved Contract Decreases:  $0   

Anticipated Completion Date:  
July 2018

Estimated Cost to Completion: 
$22,945,485.17  

PROGRESS:

November 6, 2019

  • This project is complete.

April 10, 2019

  • This project is complete with punch list and landscaping to being in spring from W. 130th Street to Pearl Road.

February 6, 2019

  • This project is complete with punch list and landscaping to being in spring from W. 130th Street to Pearl Road.

January 16, 2019

  • This project is complete apart from repairing the landscaping in the spring.

September 7, 2018

  • Section 1 (York Road to W. 130th Street) - Complete with exception of punch list and repair landscaping.
  • Section 2 A (West 130th Street to Baldwin Reserve) - Complete apart from punch list and repair landscaping. 
  • Section 2 B (Baldwin Reserve to Pearl Road) - Four out of five lanes of new pavement have been poured.
  • Sidewalk and aprons on north side are complete. 
  • Curb lane on the south side will be poured on September 11, at 1:00 a.m., Bagley Road will be closed for this day from 12:00 a.m. t0 12:00 p.m. on September 11th.  
  • Sidewalks and drive aprons will be excavated and begin to be poured the following week. 
  • Landscaping and striping to follow. 
  • Contractor will return in the Spring to repair and landscaping and striping.

March 8, 2018

  • Work is completed from York Road to Baldwin Reserve with exception of permanent landscaping on the north side from W. 130th Street to Baldwin Reserve.
  • Contractor began to install temporary pavement for the last section from Baldwin Reserve to Pearl Road. (temporary pavement is on the south side).
  • In approximately 2 weeks, two-way traffic will be maintained while work begins on new pavement on the north side.
  • Work ongoing on the installation of new traffic signals.
  • Any touch-up/repairs landscaping on the project will be done in the Spring.

December 15, 2017

Section 2: West 130th Street to Bridge 116  

  • Bagley/Pleasant Valley- all pavement sidewalks and aprons have been completed. Permanent landscaping in this section on the north side will be completed in Spring 2018.
  • Traffic heading westbound will merge from two lanes down to one lane after Bartholomew Ave.
  • Miscellaneous traffic signal work will be done over the winter.
  • All roadwork will resume in the Spring.

Section 3: Bridge 116 to Pearl Road

  • Work to begin in early 2018-will include excavation, stabilization, new concrete pavement walks, sidewalks, landscaping striping and new signals.

November 17, 2017

  • York to W. 130th Street - Section 1 Permanent traffic installation at Oakwood.
  • W. 130th Street to Baldwin Reserve- Section 2A - Traffic is currently on south side of pavement. All new pavement has been poured from W. 130th Street to Baldwin Reserve. Current work is install new aprons and sidewalks.
  • Once sidewalk and aprons are installed, most work will shut down the winter with road mostly open from W. 130th Street to Bartholomew.
  • Permanent traffic control and signals will be installed. Final landscaping in this section will be done next spring.
  • Next season anticipate finishing new pavement from Baldwin Reserve to Pearl Road.

October 10, 2017

  • Bagley/Pleasant Valley – Section 2 complete with exception of permanent traffic signals
  • Bagley/Pleasant Valley- Section 1 (W. 130th St. to Pearl Rd).
  • W. 130th Street to Baldwin Reserve south side is complete.
  • North side currently excavating and being cement stabilized.
  • Anticipate paving the north side from W. 130th Street to Baldwin Reserve within a month.
  • Residents will be notified and they will have to make arrangements for parking with their neighbors.
  • Bridge 116 north half of bridge delivered and set. Back fill operation to begin.
  • Bagley/Pleasant Valley
  • Anticipate all lanes being poured in before end of the season from W. 130th Street to Baldwin Reserve. Baldwin Reserve to Pearl Rd. will begin early next year.

September 7, 2017

Pleasant Valley Road/Bagley Road-W. 130th Street to Bridge 161: