Avery Road Bridge #01.16 - Chippewa Creek Broadview Hts

  • Notice to Proceed: 3/30/2017
  • Start Date: 3/4/2017
  • Completion Date: 12/15/2017
  • Project Amount: $1,696,926.45
  • This Page Last Updated On: 4/7/2017

Date:  April 4, 2017

Contractor: J.D. Williamson Construction

County Project Contacts:
Darwin Merdes  216 348-4073

Todd Zima      216-701-2359

Notice to Proceed: March 2017

Start Date:  March 3, 2017

Scheduled Completion Date: December 2017

Contract Award Amount: $1,696,926.45

Approved Contract Increases:  $0

Approved Contract Decreases:  $0

Anticipated Completion Date: December 2017

Estimated Cost to Completion: $1,696,926.45



PROGRESS:

  • Avery Road is closed, detour has been posted.
  • Weather dependent, installation of relocated 20" water-main.
  • Bridge demolition will begin after waterline is installed.