You are here: Home > Projects & Programs > Construction Updates 

Avery Road Bridge #01.16 - Chippewa Creek Broadview Hts

  • Notice to Proceed: 3/30/2017
  • Start Date: 3/4/2017
  • Completion Date: 12/15/2017
  • Project Amount: $1,696,926.45
  • This Page Last Updated On: 10/10/2017

Date:  April 4, 2017

Contractor: J.D. Williamson Construction

County Project Contacts:
Darwin Merdes  216 348-4073

Todd Zima  216-701-2359

Notice to Proceed: March 2017

Start Date:  March 3, 2017

Scheduled Completion Date: December 2017

Contract Award Amount: $1,696,926.45

Approved Contract Increases:  $0

Approved Contract Decreases:  $0

Anticipated Completion Date: December 2017

Estimated Cost to Completion: $1,696,926.45

PROGRESS:


October 10, 2017

  • Bridge is 95% complete.
  • Anticipated opening bridge and Avery Road by the end of October 2017.

September 7, 2017

  • Deck is poured.
  • Work continuing on parapets and road just outside of the bridge (minimal road work to accommodate new bridge). 
  •  

July 7, 2017

  • Water-main relocation complete.
  • Bridge demolition complete.
  • New piers 90% complete (north pier cap needs to be poured).
  • Pile driving for abutments 99% complete.
  • Once last pile is driven, north abutment will be poured while south abutment seat will be poured.
  • Beam delivery is scheduled for July 13th or July 18th (depending on the supplier delivery).

June 6, 2017
  • 20” water-main line relocation is 95% complete. Waiting for chlorination test to be completed. Anticipate final water line work first week in June.
  • Drilled shaft piling and pier columns completed.
  • Bridge demolition has begun. Anticipated completion of bridge demolition within 2 weeks.

Anticipated Work: 

  • Pile driving for abutments, constructing abutment footers and pier caps.
  • Avery Road is closed, detour has been posted.
  • Weather dependent, installation of relocated 20" water-main.
  • Bridge demolition will begin after waterline is installed.