- Notice to Proceed: 10/1/2018
- Start Date: 12/1/2018
- Completion Date: 10/1/2019
- Project Amount: $1,354.515.80
- This Page Last Updated On: 2/7/2019
Contractor: Karvo Paving Comapnies, Inc.
County Project Contacts:
Ryan Maver 216-560-3932
Rich Orosz 216-701-4047
Approved Contract Increases: $0
Approved Contract Decreases: $0
Anticipated Completion Date: December 2019
Estimated Cost to Completion: $1,792,814.14
PROGRESS
February 7, 2019
Work Expected in the upcoming weeks will include:
- System analysis; including video detection and timing adjustments
- Final clean-up and punch list items to be completed in the spring.
January 17, 2019
Work Expected in the upcoming weeks will include:
- Complete installation of final epoxy/thermoplastic pavement markings; Warrensville Center Road/Amazon Site Drive 1: Emery Rd./Jack Casino, Emery Rd./Northfield Rd.; Northfield Rd./Amazon Drive 6; and Northfield Rd./Miles Rd.
- This item will include painting new crosswalk lines to accommodate newly relocated/installed ADA ramps.
- New traffic Signals: The new traffic signal supports, and arms have arrived and are currently being installed at all intersections.
- Once completed and tested, existing signal and signals and controllers will be removed.
- Final clean up and punch list items to begin.
October 16, 2018
Work Expected in the upcoming weeks will include:
- Complete installation of final epoxy/thermoplastic pavement markings; Warrensville Center Road/Amazon Site Drive 1: Emery Rd./Jack Casino, Emery Rd./Northfield Rd.; Northfield Rd./Amazon Drive 6; and Northfield Rd./Miles Rd.
- This item will include painting new crosswalk lines to accommodate newly relocated/installed ADA ramps.
- New traffic Signals: The new traffic signal supports, and arms have arrived and are currently being installed at all intersections.
- Once completed and tested, existing signal and signals and controllers will be removed.
- Final clean up and punch list items to begin.
September 10, 2018
Work Expected in the upcoming weeks will include:
- ADA Ramps; Complete the installation of new concrete curb ramps at the following intersections: o Emery Rd./ Jack Casino, Emery Rd./ Northfield; Northfield Rd./ Amazon Drive 6 and Northfield; Miles Rd./Miles Rd.
- Final epoxy, thermoplastic pavement markings; o Warrensville Center Rd./Amazon Site Drive 1; Emery Rd./ Jack Casino, Emery Rd./Northfield Rd; Northfield Rd/Amazon Drive 6; and Northfield Rd./ Miles Rd.
- This item will include painting new crosswalk lines to accommodate newly relocated installed ADA ramps.
- New Traffic Signals: Contractor is continuing to install all traffic signal hardware at the various intersections; conductor and fiber optics lines, pedestrian signal heads, push buttons, new traffic light signal heads, pull boxes and loop cameras.
June 12, 2018
Current Zone:
- Southbound curb lane closure along Warrensville Center Road from Miles Road to Emery Road as road widening project is underway. Other temporary zones are implemented as needed on a daily basis.
- Two-way traffic will be maintained always.
Work:
Warrensville Road Widening (Miles to Emery):
- Continue layout and construction of drainage conduits, manholes, and catch basins be placement of 9” reinforced concrete, and new driveway apron for main entrance to the Amazon Facility.
- Warrensville/Emery; Emery/Jack Casino, Emery/Northfield; Northfield/Amazon Drive 6; and Northfield/Miles Rd. Intersection:
- Continue excavation and placement of various diameter rigid conduits, pull-boxes, and power services for signalization upgrades.
- Emery Road/Jack Casino (Drive 3) Intersection:
- Begin layout excavation and construction of proposed concrete drive apron, intersection radii and ADA curb ramps.
May, 2018
- Terrace Construction has successfully completed the installation of twenty concrete signal support foundations for traffic signal upgraded at the following intersections; Warrensville Center Drive, Warrensville @ Emery, Emery Road Drive, Emery @ Northfield, Northfield Drive and Northfield @ Miles Rd.
Work expected in the upcoming weeks will include:
- Begin layout and construction of underground drainage conduits and structures.
- Jacking/drilling and excavation for various diameter rigid conduits for signalization
- Upgrades at all intersections and drives.
- Begin layout excavation and construction of proposed right turn lanes located at Drive 6 on Warrensville Center Road.