You are here: Home > Projects & Programs > Construction Updates 

Operations Group 2-Turney Road (Hathaway Rd. to Garfield Height East Corp. Line) - Garfield Heights / Eastland /Fowles Rd -Berea South Corp. Line to Bagley Rd.-City of Berea

  • Notice to Proceed: 8/1/2016
  • Start Date: 8/1/2016
  • Completion Date: 8/30/2017
  • Project Amount: $1,211,143.20
  • This Page Last Updated On: 11/6/2017

Date: June 16, 2017

Contractor: Karvo

County Project Contacts:  Mark Rinderman 216-701-4048

Notice to Proceed: August 2016

Contract Award Amount:
  $1,211,143.20

Start Date: August  2016

Approved Contract Increases:  $36,388.25

Scheduled Completion Date: August  2017

Approved Contract Decreases:  $2,408.32

Anticipated Completion Date: August  2017

Estimated Cost to Completion:  
 $1,245,123.13

Progress For:

Operations Group 2-Turney Road (Hathaway Rd. to Garfield Height East Corp. Line) - Garfield Heights /
Eastland /Fowles Rd -Berea South Corp. Line to Bagley Rd.-City of Berea

Progress:

November 3, 2017

Turney Road:

 

  • Work to complete punch list is currently in progress.
  • Remainder of permanent pavement markings scheduled for this month, after corrective work related to asphalt wearing course in intersections is complete.
  • Work related to punch list to be completed by end of November 2017
  • First phase of Turney Road to the north of Rockside Road has been completed.
  • Remainder of work will require limited traffic control, no delays anticipated.

Eastland/Fowles Road:

  • Wearing course placement was completed 10/16/17.
  • Asphalt drive aprons work scheduled for this week. Existing drives (asphalt/aggregate) to be replaced. Grading berm to follow.
  • Epoxy pavement markings scheduled for November.
  • Fowles Road south of Eastland Road has been completed.
  • Work will require daily traffic control with flaggers during work hours.
     
  • Expect minor delays while traveling through construction zone on Eastland/Fowles.
  • No road closures for above roadway.
  • ACCESS TO ASPHALT DRIVE APRONS ON EASTLAND/FOWLES WILL BE AFFECTED BY NEW DRIVE APRON CONSTRUCTION in EARLY NOVEMBER.
  • NOTICE OF ONE WEEK TO BE SENT TO THOSE AFFECTED.

October 10, 2017


Turney Road:

 

 

 

 

  • Work completed except for permanent pavement markings, final seeding and mulching.Epoxy center line placed. 
  • Remainder of permanent pavement markings scheduled for October, after corrective work related to asphalt wearing course in intersections is complete.
  • Work related to punch list scheduled for October 2017.
  • Turney Road under construction from Hathaway road, travelling north through Garfield Heights, per separate Cuyahoga County project.
  • Remainder of work will require limited traffic control, no delays anticipated.

Eastland/Fowles Road:

  • Adjustments of castings, install of ADA compliant curb ramps complete.
  • Concrete drive aprons comple
  • Concrete (255) repairs completed.
  • Asphalt wearing course placement scheduled for week of October 9, 2017.
  • Asphalt drive aprons to be placed after wearing course install, with berm work to follow, including necessary grading.
  • Fowles Road south of Eastland Road has been completed.
  • Work will require daily traffic control with flaggers during work hours.
  • Expect minor delays while traveling through construction zone on Eastland/Fowles.
  • No road closures for above roadway
  • ACCESS TO ASPHALT DRIVE APRONS ON EASTLAND/FOWLES WILL BE AFFECTED BY NEW DRIVE APRON CONSTRUCTION in EARLY OCTOBER.
  • NOTICE OF ONE WEEK TO BE SENT TO THOSE AFFECTED
September 6, 2017
Turney Road:

  • Work completed except for permanent pavement markings, final seeding and mulching.
  • Epoxy center line placed.
  • Remainder of permanent pavement markings scheduled for September/October, after corrective work related to asphalt wearing course in intersections is complete.
  • Work related to punch list scheduled for September/October 2017.
  • Turney Road under construction from Hathaway road, travelling north through Garfield Heights, per separate Cuyahoga County project.
  • Remainder of work will require limited traffic control, no delays anticipated.
  • Eastland/Fowles Road:
  • Adjustments of castings, install of ADA compliant curb ramps complete.
  • Concrete drive aprons complete.
  • Concrete (255) repairs in progress, to be completed next week.
  • Asphalt drive aprons to be placed throughout project after final paving work is complete.
  • Placement of asphalt wearing course scheduled for week of September 11th.
  • Berm work to be performed after final paving is complete, including necessary grading.
  • Fowles Road south of Eastland Road will be under construction at same time per City of Middleburg Heights project.
  • Work will require daily traffic control with flaggers during work hours
  • Expect delays while traveling through construction zone on Eastland/Fowles.
  • ACCESS TO ASPHALT DRIVE APRONS ON EASTLAND/FOWLES WILL BE AFFECTED BY NEW DRIVE APRON CONSTRUCTION MID SEPTEMBER.
  • NOTICE OF ONE WEEK TO BE SENT TO THOSE AFFECTED.
August 3, 2017
Turney Road:
 

  • Work completed except for permanent pavement markings, final seeding and mulching.
  • Permanent pavement (center line) markings scheduled for August.
  • Work related to punch list items, scheduled for August/September 2017.
  • Remainder of work will require limited traffic control, no delays anticipated.
    Eastland/Fowles Road:
  • Repairs to roadway, chip seal and intermediate asphalt course have been completed.
  • Adjustments of castings, install of ADA compliant curb ramps currently in progress.
  • Drive aprons will be addressed, placement of asphalt wearing course.
  • Work will require daily traffic control with flaggers during work hours
  • Expect delays while traveling through construction zone on Eastland/Fowles.
  • No road closured are anticipated for above roadways. 
  • ACCESS TO ALL RESIDENTIAL DRIVERS WILL BE MAINTAINED AT ALLTIMES.
  • Resurfacing of .44 miles of Hathaway Road.
  • Project substantially completed.
  • Asphalt surface course placed.
  • Permanent pavement markings placed
  • Road is open to traffic.
July 13, 2017

Turney Road:


  • Work completed with the exception of permanent pavement markings, final seeding and mulching.
  • Punch list items to be completed.
Eastland/Fowles Road:

  • Two-way traffic will be maintained by use of flaggers during work hours.
  • Expect delays while traveling through construction zone on Eastland/Fowles Road.
  • No road closures are anticipated for above roadway.
  • Access to all residential drives will be maintained at all times.
June 16, 2017

Turney Road
  • Work completed with the exception of permanent pavement markings, final seeding and mulching.
  • Punch list items to be completed
Eastland/Fowles Road:
  • Pavement planning, repairs and placement of intermediate asphalt course scheduled for June.
  • Two-way traffic will be maintained by use of flaggers during work hours.
  • Expect delays while traveling through construction zone on Eastland/Fowles Road.
  • No road closures are anticipated for above roadway.
  • Access to all residential drives will be maintained at all times.