2016 Operations Group 2 - Garfield Hts. East & Berea South Corporate Line

  • Notice to Proceed: 8/1/2016
  • Start Date: 8/1/2016
  • Completion Date: 8/30/2017
  • Project Amount: $1,211,143.20
  • This Page Last Updated On: 7/13/2017

Date: June 16, 2017

Contractor: Karvo
County Project Contacts:  Mark Rinderman 216-701-4048

Notice to Proceed: August 2016

Contract Award Amount:  $1,211,143.20

Start Date: August  2016

Approved Contract Increases:  $36,388.25

Scheduled Completion Date: August  2017

Approved Contract Decreases:  $2,408.32

Anticipated Completion Date: August  2017

Estimated Cost to Completion:  
 $1,245,123.13

Progress:

July 13, 2017

Turney Road:

  • Work completed with the exception of permanent pavement markings, final seeding and mulching.
  • Punch list items to be completed.

Eastland/Fowles Road:

  • Two-way traffic will be maintained by use of flaggers during work hours.
  • Expect delays while traveling through construction zone on Eastland/Fowles Road.
  • No road closures are anticipated for above roadway.
  • Access to all residential drives will be maintained at all times.

June 16, 2017

Turney Road

Work completed with the exception of permanent pavement markings, final seeding and mulching.

  • Punch list items to be completed

Eastland/Fowles Road:

  • Pavement planning, repairs and placement of intermediate asphalt course scheduled for June.
  • Two-way traffic will be maintained by use of flaggers during work hours.
  • Expect delays while traveling through construction zone on Eastland/Fowles Road.
  • No road closures are anticipated for above roadway.
  • Access to all residential drives will be maintained at all times.