Wallings Road City of Broadview Heights

  • Notice to Proceed: 7/1/2018
  • Start Date: 8/2/2018
  • Completion Date: 11/29/2018
  • Project Amount: $1,251,754.00
  • This Page Last Updated On: 1/16/2019

Contractor:
Kokosing Construction Company
(216)467-7705 

County Project Contacts: 
Terry Cain (216) 633-0567  
Ryan Maver (216) 759-2472 

Notice to Proceed: July 2018
Contract Award Amount:  $1,215,754.00

Start Date:  August 2018
Approved Contract Increases:  $0

Scheduled Completion Date:
November 2018

Approved Contract Decreases:  $ 0

Anticipated Completion Date: November 2018

Estimated Cost to Completion:   $1,251,754.00


PROGRESS:

January 4, 2019
  • Asphalt placement has been completed between I-77 and Broadview Road 
  • Asphalt will be placed between I-77 and the Brecksville Corporation Line in the spring as well as landscaping work will commence.

December 6, 2018
  • 1 ¾ inches of leveling course asphalt has been placed.
  • Castings in the roadway have been adjusted to grade.
  • New concrete and asphalt drive aprons have been placed.
  • New walk and curb ramps have been placed.
  • 1 ¼ asphalt surface course has been placed over two sections of Wallings Road.
  • Two additional sections and intersections need surface course asphalt which will be placed in December weather permitting.